Showing posts with label South San Francisco. Show all posts
Showing posts with label South San Francisco. Show all posts

Friday, March 11, 2016

Time to Spring Forward!


It is starting to look a lot like spring on the Peninsula. One of our team members snapped this picture of some Golden Poppies from the Peninsula Pipeline Seismic Upgrade project site in South San Francisco. In addition, it is time to spring forward with Daylight savings time starting this Sunday, March 13, 2016. Don’t forget to turn your clocks forward one hour for more light in the evening and a later sunrise! Hello Spring!

Friday, December 18, 2015

Happy Holidays from Hetch Hetchy Regional Water System!

Thank you for being wonderful customers and neighbors throughout construction in 2015. It has been a busy year on the Peninsula, the SFPUC’s Water System Improvement Program (WSIP) celebrated the completion of the Harry Tracy Water Treatment Plant in San Bruno and the last major water transmission pipeline in the Peninsula region coming into service.

While the Water System Improvement Program overall is now 90 percent complete, we still have a long way to go and our crews are hard at work this holiday season. Below are the construction schedules for the Peninsula Pipeline Seismic Upgrade, Regional Groundwater Storage & Recovery Projects and the San Andreas Pipeline #2 at Junipero Serra Park.
  • Construction will be suspended Thursday, December 24 through Sunday, December 27.
  • Construction will be suspended Thursday, December 31 through Sunday, January 3.
  • Regular construction schedules will resume Monday, January 4.

Tuesday, July 14, 2015

Regional Groundwater Storage & Recovery Project to Begin Drilling in South San Francisco

Beginning as early as Wednesday, July 15, the San Francisco Public Utilities Commission’s Regional Groundwater Storage and Recovery (GSR) project will begin drilling a new groundwater well to a depth of 620 feet deep at Garden Chapel Funeral Home in South San Francisco.


24-hour well drilling work will occur continuously for up to one month inside the blue rectangle pictured above. 


To minimize noise impacts, the contractor will monitor noise levels and install sound blankets to ensure it does not exceed the local noise ordinance. During night work, the contractor will rotate construction lighting to direct it away from homes near well drilling work. 

Questions?
For more information about this project, please call the 24-hour answering service at 866-973-1476, or visit the Project webpage at sfwater.org/GSR. 

Tuesday, July 7, 2015

New Interactive Map for Regional Groundwater Storage & Recovery Project

The Regional Groundwater Storage & Recovery (GSR) Project has multiple active sites across five cities: Daly City, South San Francisco, Millbrae, Colma and San Bruno. In an effort to keep you informed about construction activities, detours and other project updates associated with GSR Project’s 13 sites, we have developed a Geographic Information System (GIS) Map.

This GIS map will be located on the project webpage www.sfwater.org/GSR. The map will be updated regularly depending on construction activities. A a snapshot of the GIS map with functionality capabilities is below.




  • Click numbers 1 - 13 to review construction site information
  • Each site has a box that highlights current status, hours and upcoming work
  • The blue area illustrates the construction area limits associated with the site
  • Use the navigational + and - sign to zoom in and out of the GSR project map

Sunday, May 17, 2015

GSR Project Construction Activities Ramp-up this Week

The Regional Groundwater Storage and Recovery (GSR) Project will ramp-up construction activities inside the San Francisco Public Utilities Commission’s (SFPUC)’s right of way in South San Francisco this week. 
 
Linear Park in South San Francisco
  • The contractor will begin well redevelopment work on Monday, May 18, increasing activity at this site for approximately two weeks. 
  • Permitted construction hours for this work are currently Monday through Sunday from 7 a.m. to 7 p.m.
  • Expect to see more construction vehicles accessing the site via South Spruce Avenue. Also there may be some dust and noise associated with construction activities.

Hickey Boulevard & Camaritas Avenue in South San Francisco
  • The contractor will begin well redevelopment work on Thursday, May 28, increasing activity at this site for approximately two weeks.
  • Permitted construction hours are currently Monday through Sunday from 7 a.m. to 7 p.m. 
  • Expect to see more construction vehicles accessing the site via Camaritas Avenue. There may be some dust and noise associated with construction activities. 
For more information about the GSR Project, please be sure to subscribe to this blog, visit sfwater.org/GSR or by calling us at (866) 973-1476.

Friday, January 9, 2015

South San Francisco Construction Update

Baden Valve Lot Construction 

On Monday, January 12, the PPSU project contractor, Ranger Pipelines, Inc., will begin replacing three critical valves within the San Francisco Public Utilities Commission (SFPUC)’s right of way in South San Francisco between Southwood Drive and West Orange Avenue.

These valves are critical to the Hetch Hetchy Regional Water System in the Peninsula. As a result, the contractor must replace all three valves in five days in order to put them back into operation by Friday, January 16.

With this limited construction time frame, the contractor will work 24-hour shifts for this five day period. To minimize noise impacts, the contractor will refrain from using loud equipment and back-up alarms after 8 p.m. 24-hour noise monitoring will occur to ensure noise does not exceed the City of South San Francisco’s noise ordinance and construction lighting will be pointed away from homes.


Construction project limits near Garden Chapel Funeral Home in South San Francisco.

Westborough Boulevard & Orange Avenue Construction

The project contractor, Ranger Pipelines, Inc., has completed construction of the new tunnel shafts under Westborough Boulevard. The SFPUC’s water pipelines will be taken out of service on Saturday, January 10 and the contractor will begin installing the new pipeline under Westborough Boulevard. Permitted construction hours are Monday through Friday from 8 a.m. to 8 p.m. and Saturday from 9 a.m. to 8 p.m. These construction activities are expected to last through March 2015. 


Construction project limits at Westborough Boulevard and Orange Avenue in South San Francisco.

What is the PPSU project?
The PPSU project includes the seismic upgrade of three Hetch Hetchy regional water delivery pipelines located in Northern San Mateo County. This project will ensure the pipelines can continue to deliver water to customers after an emergency.

For more information, please subscribe to this blog to receive project updates or call (866) 973-1476.

Monday, December 29, 2014

Night Work in South San Francisco Begins in January

On Monday, January 12, the PPSU project contractor, Ranger Pipelines, Inc., will begin replacing three critical valves within the San Francisco Public Utilities Commission (SFPUC)’s right of way in South San Francisco between Southwood Drive and West Orange Avenue.

These valves are a critical to the Hetch Hetchy Regional Water System in the Peninsula. As a result, the contractor must replace all three valves in five days in order to put them back into operation by Friday, January 16.

With this limited construction time frame, the contractor will work 24-hour shifts for this five day period. To minimize noise impacts, the contractor will refrain from using loud equipment and back-up alarms after 8 p.m. 24-hour noise monitoring will occur to ensure noise does not exceed the City of South San Francisco’s noise ordinance and construction lighting will be pointed away from homes.

The PPSU project includes the seismic upgrade of three Hetch Hetchy regional water delivery pipelines located in Northern San Mateo County. This project will ensure the pipelines can continue to deliver water to customers after an emergency.

For more information, please call the 24-hour answering service at 866-973-1476, or subscribe to this blog. 

Outlined above are the construction limits where 24-hour shifts will occur Monday, January 12 through Friday, January 16. The green triangles indicate the location for valve replacement inside the work area.

Wednesday, November 26, 2014

Happy Thanksgiving from the PPSU Project!


The Peninsula Pipeline Seismic Upgrade (PPSU) Project wishes you and your family a Happy Thanksgiving. The contractor, Ranger Pipelines, Inc. will suspend construction activities starting on Thursday, November 27 through Sunday, November 30, 2014. PPSU construction is scheduled to begin again on Monday, December 1 in Millbrae, San Bruno and South San Francisco.

Permitted construction hours:

  • Millbrae - Monday through Friday from 7:30 a.m. to 7 p.m. 
  • South San Francisco - Monday through Friday from 8 a.m. to 8 p.m. and Saturday from 9 a.m. to 6 p.m.
  • San Bruno - Monday through Friday from 7 a.m. to 7 p.m.
The PPSU project is seismically upgrading three Hetch Hetchy regional water delivery pipelines located in Northern San Mateo County. This project will ensure the pipelines can continue to deliver water to customers after an emergency.

For more information, please call the 24-hour answering service at 866-973-1476, or subscribe to this blog to receive project updates.

Friday, November 21, 2014

PPSU Construction Updates: South San Francisco & Colma Sites


Crews installing new pipeline at the Millbrae site in early November.


South San Francisco

The Peninsula Pipeline Seismic Upgrade (PPSU) project contractor, Ranger Pipelines, Inc., continues construction on both sides of Westborough Boulevard inside the San Francisco Public Utilities Commission’s (SFPUC)’s right-of-way in South San Francisco. Permitted construction hours in South San Francisco are Monday through Friday from 8 a.m. to 8 p.m. and Saturday from 9 a.m. to 6 p.m. After the underground tunnel is constructed under Westborough Boulevard, the contractor will install the new pipeline in January 2015. This tunnel design was selected to not obstruct traffic along Westborough Avenue.

Colma


The contractor started construction activities along the SFPUC’s right-of-way in Colma on Monday, November 17. This work includes removing debris within the right-of-way, setting up the construction staging areas, and installing construction fences along the SFPUC right-of-way to indicate the limits of construction. Construction hours are currently Monday through Friday from 7 a.m. to 5 p.m. The contractor will begin removing and replacing approximately 700 feet of aged pipeline in January 2015.

The PPSU project includes the seismic upgrades of three Hetch Hetchy regional water delivery pipelines located in Northern San Mateo County. This project will ensure the pipelines can continue to deliver water to customers after an emergency. For more information, please call the 24-hour answering service at 866-973-1476, or subscribe to this blog to receive project updates.

Monday, August 11, 2014

PPSU Pre-construction Activities Start Today in South San Francisco




















Today the project contractor, Ranger Pipelines, Inc., will begin pre-construction activities for the Peninsula Pipeline Seismic Upgrade (PPSU) inside the San Francisco Public Utilities Commission (SFPUC)’s right of way in South San Francisco. Work will occur Monday through Friday from 7 a.m. to 5 p.m. Please keep an eye out for intermittent sidewalk closures and detours on Arroyo Drive and Westborough Boulevard.

The contractor will clear the project site of materials and brush within the right of way and begin potholing to locate existing underground utilities. The contractor will begin construction of a new tunnel across Westborough Boulevard in October 2014. The installation of the new pipeline from West Orange Avenue to Arroyo Drive will start in January 2015.

The PPSU project includes the seismic upgrade of three Hetch Hetchy regional water delivery pipelines located in Northern San Mateo County. This project will ensure the pipelines can continue to deliver water to customers after an emergency. For more information, please subscribe to this blog to receive project updates.

Wednesday, June 25, 2014

WSIP’s Last Pipeline Project Begins August 2014!


The Peninsula Pipelines Seismic Upgrade (PPSU) is starting construction! The construction contract was awarded to Ranger Pipelines, Inc. Pre-construction work is already underway with construction activities scheduled to begin in August 2014.

The PPSU project consists of seismic upgrades to three critical water delivery pipelines in Northern San Mateo County. These upgrades are needed to ensure drinking water delivery to our customers following an earthquake. We will replace segments of the pipeline, open-trench construction, surface restoration and installing structural support within an existing tunnel.

The PPSU project spans six improvement components in four different cities on the San Francisco Peninsula within San Mateo County: Millbrae, South San Francisco, San Bruno and Colma. For more details, view the project fact sheet here.

This pipeline project is one of more than 80 water improvement projects that are part of the Hetch Hetchy Water System Improvement Program (WSIP). The PPSU project is the final pipeline replacement project in the WSIP program.

To kick off construction, the PPSU project team will host an open house event on Thursday, July 24 at the City of Millbrae Public Library (1 Library Avenue, Millbrae, CA, 94030). The public is invited to talk with the project team about upcoming construction activities between 5:30 p.m. and 7:30 p.m. To receive project updates, please subscribe to this blog or visit our project web page www.sfwater.org/PPSU.