Thursday, December 31, 2009
Possible Night Work in early January
During this night work, the majority of activities take place inside the shaft and tunnel. The crane and site lights may be used. The project team will follow all required nighttime noise limits as specified in the project Environmental Impact Report (EIR). Some soil may be lifted from the shaft but will not be relocated to the upper terrace until the following daytime shift.
We will continue to have on-call staff monitoring the situation. You may call our 24 hour dispatch 650-872-5900.
Monday, December 28, 2009
New Video Highlights WSIP Progress
Tuesday, December 22, 2009
North Shaft Update
The valves and pipes within the vault have now been installed and the cast-in-place concrete foundation and walls have been poured.
Tunnel boring continues from the South Shaft, heading in the direction of the North Shaft.
The project team wishes everyone Happy Holidays and a Happy New Year.
Friday, December 18, 2009
Did You Know? Way Cool Stats about the TBM
Okay, I admit that these stats are way cool, even for non-engineers.
The tunnel boring machine (TBM) in use to create the New Crystal Springs Bypass Tunnel has 23 disc cutters in the cutterhead and they are each 17 inches in diameter.
It has a torque of 593,920 foot-lbs and an operating thrust of 1,150,000 lbs operating.
It has 5 gantry cars in its trailing gear, 2 muck conveyors and the total length of the shield and trailing gear is 155 feet.
Here is a photo showing part of its 155 foot long length during assembly in September.
TBM Making Progress in Tunnel!
As of this week, the TBM has mined 401 feet so far, and with the starter tunnel distance included, that brings us to 532 feet or 12.4% complete.
Here is a photo from the bottom of the South Shaft.
Friday, December 4, 2009
Happy Holidays from the New Crystal Springs Bypass Tunnel project staff
Friday, November 20, 2009
Night Work Nov 24-25, 30 and Dec 1st
During this night work, the majority of activities take place inside the shaft and tunnel. The crane and site lights may be used. The project team will follow all required nighttime noise limits as specified in the project Environmental Impact Report (EIR). Some soil may be lifted from the shaft but will not be relocated to the upper terrace until the following daytime shift.
We will continue to have on-call staff monitoring the situation. You may call our 24 hour dispatch 650-872-5900.
Thursday, November 19, 2009
UC Berkeley Engineering Students Tour South Shaft Site
Members of the project team led the tour and shared information about the project.
The students are taking an engineering geology class through UC Berkeley's Department of Civil and Environmental Engineering.
Friday, November 13, 2009
Safety Reminders on Polhemus Road
We are committed to safety and recently posted new signs on Polhemus Road alerting drivers, cyclists and pedestrians about trucks entering and exiting the roadway near our South Shaft site.Please use caution in the area as we expect more trucks entering and exiting the site when we begin boring the tunnel.
Please also watch for deer! They often graze on the side of Polhemus Road and often cross in front of traffic. Please watch speed and use caution.
Thursday, November 12, 2009
Temporary Night Work to Begin Friday, November 13th
During the night work, a smaller crew of workers will be on site and the majority of the work will take place inside the shaft and tunnel. The crane and site lights will be in use. The project team will follow all required nighttime noise limits as specified in the project Environmental Impact Report (EIR). Some soil may be lifted from the shaft but will not be relocated to the upper terrace until the following daytime shift.
Maureen Barry will be available at 415-350-4929 or via email at mbarry@sfwater.org after 7pm in case neighbors have concerns. She will have direct access to the field supervisor.
What Neighbors Can Expect in November and December
Neighbors near the South Shaft site will see crews continuing to work inside the shaft, tunnel and maintenance shop. If critical adjustments are successful, tunnel boring is expected to begin in mid to late November. As stated in the EIR and during public meetings, tunnel boring may take place 24 hours a day if necessary.
Friday, November 6, 2009
November Update
The holidays will be here soon! We do not plan to work on the following dates: November 26 and 27. December 25 and January 1st.
Here is a recent photo of the South Shaft site showing the precast concrete segments that will be installed inside the tunnel.
Thursday, November 5, 2009
Crews to begin Preliminary Potholing in Daly City on Monday

The preliminary stages of potholing of the construction project will consist of crews verifying the existing placement of pipelines and other utilities in the following locations:
Wilshire Avenue to Sheffield Drive 7 a.m. - 5 p.m.
Sheffield Drive to John Daly Boulevard 7a.m. - 5p.m.
John Daly Boulevard to Poncetta Drive 7a.m. - 5p.m.
Potholing is expected to be completed by December 2009.
For continuing updates on this project, please visit www.sfwater.org/sanandreas3
Friday, October 30, 2009
Work Lights on Site
With the end of Daylight Savings Time this weekend, work crews will need to turn on work lights earlier starting on Monday, November 2nd.
The work lights face downward to prevent light from shining into neighborhood homes. If you have any concerns, contact us via this blog or at 650-212-0165.
Don't forget to turn your clocks back on Sunday, November 1st! Happy Halloween!
Tuesday, October 27, 2009
Safe Roadways: Two Tips for Safety Near our Worksites
With tunnel boring beginning at the South Shaft soon, the contractor expects a slight increase in truck traffic entering and exiting the site on Polhemus Road. The project is committed to safety and will remind all truck drivers to use caution when driving, entering and exiting on Polhemus Road. Please watch for these trucks entering and exiting the site during work hours. For the safety of everyone, please follow the posted speed limit on Polhemus Road.
10 MPH Speed Limit on Crystal Springs Road
Please also remember the 10 mile per hour speed limit on Crystal Springs Road near the intersection of Polhemus at the site of our North Shaft. The section is 10 mph to ensure safety for bicycle riders, pedestrians, cars and the work teams at the site. Please follow the posted speed limit at all times. Thank you.
Thursday, October 22, 2009
Views from the Tunnel
The first photo is a shot of the Tunnel Boring Machine trailing gear inside the starter tunnel.
Thursday, October 1, 2009
TBM Successfully Lowered into South Shaft on Sept 30th
Special thanks to the many skilled workers and staff, and especially crane operator Lawrence Cary, who worked calm and steady to lower the TBM 155 feet down into the shaft.
Tuesday, September 29, 2009
Update! TBM Lowering on Wednesday, Sept 30th!
The massive Tunnel Boring Machine (TBM) is scheduled to be lowered into the South Shaft starting around 7am on Wednesday, September 30th. The process could take several hours, depending on conditions at the site. Be sure to watch from your homes and send us any photos you take!
We will post photos and possibly video in the next week! The TBM and other equipment will be placed in the shaft over the next week. In October, they will begin boring the New Crystal Springs Bypass Tunnel under Polhemus Road.
Please Respect Safety: The project team has noticed golf balls at the South Shaft site. Please respect safety and do not hit golf balls onto the site as they have the potential to severely injure workers and staff and cause severe damage to equipment.
Friday, September 25, 2009
TBM Lowering into South Shaft on Sept 29 or 30th

The Tunnel Boring Machine (TBM) will be lowered into the South Shaft next week - on either Sept 29th or 30th, depending on conditions at the site.
The TBM will be used to bore the New Crystal Springs Bypass Tunnel under Polhemus Road. The amazing machine will eat through rock and other materials to bore the 4,200 foot long tunnel.
Watch this blog for the updated date and time the TBM will be lowered.
Neighbors - we would love to see photos you take from your homes during the TBM lowering! Please contact us via the blog and we will upload photos.
Thursday, September 24, 2009
Please join us on the Sawyer Camp Trail on Saturday, Sept 26th!

Friday, September 18, 2009
Neighbors Get Inside Look at TBM during Launch Event on Sept 18th
Thursday, September 17, 2009
Friday at 11am: Preview the TBM
Monday, September 14, 2009
San Mateo County Officials Visit
Last week, WSIP Director Julie Labonte toured the tunnel job site and shaft with San Mateo County representatives who were interested in our progress and seeing the tunnel boring machine. Pictured from left to right Husam Masri, Regional Project Manager; Diana Shu and Joe LoCoco of San Mateo County, WSIP Director Labonte, and Curtis Bahten, Project Superintendent.
Join us on Friday to inspect the Tunnel boring machine (TBM) yourself.
Thursday, September 3, 2009
You're Invited! TBM Launch September 18th!
SFPUC to begin Prepping for Installation of San Andreas Pipeline No. 3
Work will commence near the County line and proceed north. Construction south of John Daly Boulevard will begin after January 2010.
In early September, SFPUC will begin preliminary stages of the construction project by potholing, or verifying the existing placement of pipelines and other utilities. Potholing is expected to be completed by the end of October 2009.
What to expect?
Contractor will need to restrict parking around locations where potholing will take place. Advance notice will be given 72-hours in advance.
If work is not commenced prior to noon, parking is available to the public.
Workdays and Hours
Monday-Friday 7:00 am - 5:00 pm
No construction will occur outside of these posted hours without advanced written notice.
Traffic
Minimal traffic impact, possible detours.
Noise
Noise levels will be in compliance with San Francisco Noise Ordinance and the noise will be limited to the immediate work areas.
Complete construction duration for San Andreas Pipeline No. 3 will be from:
September 2009 - January 2012
For more information on San Andreas Pipeline No. 3, please visit sfwater.org/wsip
Tuesday, September 1, 2009
San Andreas Pipeline No. 3 Installation Notice
Please look out for the 30-day construction notice.
Monday, August 31, 2009
Valve Lot Improvements begin in South San Francisco and Daly City
Construction work on various upgrades and improvements at the Baden Valve Lot in South San Francisco, and the San Pedro Valve Lot in Daly City has started. This work is critical to provide local residents with reliable drinking water.
Construction Duration
South San Francisco:
Monday to Friday: 8:00 am-5:00 pm.
Duration: May 2009 – Spring 2011
Daly City:
Monday to Friday: 7:30 am -5:00 pm
Duration: May 2009 – Winter 2009
Construction noise can be expected during these times, but is not anticipated to exceed local noise ordinances. Noise monitoring will be performed throughout construction. On occasion, minor traffic impacts during equipment deliveries can be expected. No parking impacts are anticipated. We will notify neighborhoods and businesses individually for any major construction activities.
Controlled Blasting Comes to an End!!
We will alert everyone if the contractor needs to blast again in the future but at this time, no controlled blasts are scheduled.
Thank you to all neighbors for your patience during the controlled blasting. We know you've heard and felt them and we appreciate your support and patience through this difficult part of the project.
We are planning a public event at the South Shaft site in September so everyone can see the Tunnel Boring Machine. More details soon!
Friday, August 28, 2009
Controlled Blasts Nearing Completion!
All indicators for vibration, noise and air quality are below the thresholds and are measured constantly.Controlled blasting can take place between 7am and 6pm Monday through Friday.
All safety and noise control measures are in effect and the work is performed in accordance with California Occupational Safety and Health (OSHA) and environmental regulations.
Tuesday, August 25, 2009
Controlled Blast Schedule for August 26-28
All indicators for vibration, noise and air quality are below the thresholds and are measured constantly.Controlled blasting can take place between 7am and 6pm Monday through Friday.
All safety and noise control measures are in effect and the work is performed in accordance with California Occupational Safety and Health (OSHA) and environmental regulations.
Friday, August 21, 2009
Controlled Blasts Drawing to a Close
Tuesday, August 18, 2009
Blast Schedule for Remainder of Week
The anticipated finish time for the controlled blasts is about one month or less with 4-5 shots per week. The starter tunnel is now 80 feet long. Final length will be approximately 100 feet.
The contractor continues to perform within the thresholds for noise, vibration and air quality standards. Measurements are conducted daily.
Dust Mitigation
The project contractor has implemented additional mitigation measures in response to dust complaints from neighbors.
Monday, August 17, 2009
No Blast scheduled for Tuesday
Friday, August 14, 2009
A Look Inside the Shaft
Friday blast around noon; end of double blasts
All indicators for vibration, noise and air quality are below the thresholds and continue to be measured constantly. Late today, check out photos from inside the tunnel.
Wednesday, August 12, 2009
Neighbor Helps Get the Job Done
This morning, Gene Ciranni, on right, a neighbor from Ascension Drive, helped Jim Mulkey, one of the contractor's superintendent's and a licensed blaster, set off the second underground blast around 10:30 am. On Thursday, there will be only one blast, and it is scheduled between 11 and 11:30 am.
Tuesday, August 11, 2009
Controlled Blast Tuesday around 9 am, Two Wed.
Friday, August 7, 2009
Controlled Blasts for Week of 8/10
All indicators for vibration, noise and air quality are below the thresholds and are measured constantly. We were pleased to hear that Thursday's blast was less disruptive for neighbors. The Construction Manager noted that atmospheric conditions were different yesterday and cloud cover and wind (or lack of both) have a big impact on perception of sound pressure at a distance that translates into the shaking that neighbors feel.
The contractor intends to perform controlled blasting once or twice a day between 7am and 6pm Monday through Friday through the week of August 17. All safety and noise control measures are in effect and the work is performed in accordance with California Occupational Safety and Health (OSHA) and environmental regulations.
As you may know, Amy Sinclair is on vacation through August 21. I will be coordinating directly with you through that time. Maureen
Tuesday, August 4, 2009
Controlled Blast Schedule Update - Week of August 3rd
All indicators for vibration, noise and air quality are below the thresholds and are measured constantly.
Controlled blasting can take place between 7am and 6pm Monday through Friday.All safety and noise control measures are in effect and the work is performed in accordance with California Occupational Safety and Health (OSHA) and environmental regulations.
Friday, July 31, 2009
Project Update/Bike Race on Sunday. Aug 2nd
The contractor is forming the starter and tail tunnels at the bottom of the South Shaft. The tunnel boring machine (TBM) is being assembled on site and will begin its work in early October.
Watch for new photos soon!
Tour de Peninsula on Sunday, August 2nd
Local residents may notice bike riders on local roads on Sunday, August 2nd. The Tour de Peninsula 2009 returns to the area! To make sure the roads are as clean as possible, the contractor used a street sweeper machine this week on roads near our project.
Please watch the roads around San Mateo for bike riders on Sunday!
10 MPH Speed Limit Posted at Crystal Springs/Polhemus
And a reminder that the posted speed limit on Crystal Springs Road near the intersection of Polhemus Road at the site of our North Shaft is 10 mph at all times while posted during our project. This speed limit is for everyone's safety. And please always watch for bikes and pedestrians in that area.
Controlled Blasts Scheduled for August 3 - 7 for starter and tail tunnels
All indicators for vibration, noise and air quality are below the thresholds and are measured constantly.
Controlled blasting can take place between 7am and 6pm Monday through Friday.All safety and noise control measures are in effect and the work is performed in accordance with California Occupational Safety and Health (OSHA) and environmental regulations.
Tuesday, July 28, 2009
Controlled Blasts Scheduled for July 29th - 31st
All indicators for vibration, noise and air quality are below the thresholds and are measured constantly.
Controlled blasting can take place between 7am and 6pm Monday through Friday.All safety and noise control measures are in effect and the work is performed in accordance with California Occupational Safety and Health (OSHA) and environmental regulations.
Monday, July 27, 2009
Controlled Blast Scheduled for July 28th in afternoon
All indicators for vibration, noise and air quality are below the thresholds and are measured constantly.
Controlled blasting can take place between 7am and 6pm Monday through Friday.All safety and noise control measures are in effect and the work is performed in accordance with California Occupational Safety and Health (OSHA) and environmental regulations.
Controlled Blast Scheduled for Monday, July 27th
All indicators for vibration, noise and air quality are below the thresholds and are measured constantly.
Controlled blasting can take place between 7am and 6pm Monday through Friday.All safety and noise control measures are in effect and the work is performed in accordance with California Occupational Safety and Health (OSHA) and environmental regulations.
Friday, July 24, 2009
Controlled Blast Scheduled for Friday, July 24th
All indicators for vibration, noise and air quality are below the thresholds and are measured constantly.
Controlled blasting can take place between 7am and 6pm Monday through Friday.All safety and noise control measures are in effect and the work is performed in accordance with California Occupational Safety and Health (OSHA) and environmental regulations.
Wednesday, July 22, 2009
Controlled Blast Scheduled for July 23rd after 1pm
All indicators for vibration, noise and air quality are below the thresholds and are measured constantly.
Controlled blasting can take place between 7am and 6pm Monday through Friday.All safety and noise control measures are in effect and the work is performed in accordance with California Occupational Safety and Health (OSHA) and environmental regulations.
Tuesday, July 21, 2009
Controlled Blast Scheduled for Wednesday, July 22nd
All indicators for vibration, noise and air quality are below the thresholds and are measured constantly.
Controlled blasting can take place between 7am and 6pm Monday through Friday.All safety and noise control measures are in effect and the work is performed in accordance with California Occupational Safety and Health (OSHA) and environmental regulations.
Monday, July 20, 2009
New Site Photos!
Thursday, July 16, 2009
The Tunnel Boring Machine is here!
Controlled Blast Scheduled for Monday, July 20th.
All indicators for vibration, noise and air quality are below the thresholds and are measured constantly.Controlled blasting can take place between 7am and 6pm Monday through Friday.
All safety and noise control measures are in effect and the work is performed in accordance with California Occupational Safety and Health (OSHA) and environmental regulations.
Monday, July 13, 2009
Controlled Blasts Scheduled July 13th & 14th
All indicators for vibration, noise and air quality are below the thresholds and are measured constantly.
Controlled blasting can take place between 7am and 6pm Monday through Friday.All safety and noise control measures are in effect and the work is performed in accordance with California Occupational Safety and Health (OSHA) and environmental regulations.
Thursday, July 2, 2009
Controlled Blasts Scheduled for July 7th & 8th
All indicators for vibration, noise and air quality are below the thresholds and are measured constantly.
Good news! The South Shaft has reached a depth of nearly 150 feet and will be ready this summer/early fall for the tunnel boring machine. Blasts at the South Shaft (to form the tunnel) will continue through the summer and will hopefully end in September or October or earlier.
Controlled blasting can take place between 7am and 6pm Monday through Friday.All safety and noise control measures are in effect and the work is performed in accordance with California Occupational Safety and Health (OSHA) and environmental regulations.
Wednesday, July 1, 2009
Controlled Blast Scheduled July 1st at North Shaft
All indicators for vibration, noise and air quality are below the thresholds and are measured constantly.
Controlled blasting can take place between 7am and 6pm Monday through Friday.All safety and noise control measures are in effect and the work is performed in accordance with California Occupational Safety and Health (OSHA) and environmental regulations.
Monday, June 29, 2009
Tunnel Boring Machine to arrive at South Shaft in early July!

Controlled Blast Scheduled for June 30th or July 1st
All indicators for vibration, noise and air quality are below the thresholds and are measured constantly. Controlled blasting can take place between 7am and 6pm Monday through Friday.
All safety and noise control measures are in effect and the work is performed in accordance with California Occupational Safety and Health (OSHA) and environmental regulations.
The contractor will observe our national holiday on Friday, July 3rd.
Tuesday, June 23, 2009
Controlled Blast Scheduled for June 24th or 25th
All indicators for vibration, noise and air particulates are below the thresholds and are measured constantly.
Controlled blasting can take place between 7am and 6pm Monday through Friday. All safety and noise control measures are in effect and the work is performed in accordance with California Occupational Safety and Health (OSHA) and environmental regulations.
Thursday, June 18, 2009
Join us for Coffee at Starbucks on June 24th at 9am!
Wednesday, June 17, 2009
Controlled Blast Scheduled for Friday, June 19th
All indicators for vibration, noise and air particulates are below the thresholds and are measured constantly.
Controlled blasting can take place between 7am and 6pm Monday through Friday. All safety and noise control measures are in effect and the work is performed in accordance with California Occupational Safety and Health (OSHA) and environmental regulations.
Friday, June 12, 2009
Controlled Blasting Schedule for Week of June 14th
All indicators for vibration, noise and air particulates are below the thresholds and are measured constantly.
Controlled blasting can take place between 7am and 6pm Monday through Friday. All safety and noise control measures are in effect and the work is performed in accordance with California Occupational Safety and Health (OSHA) and environmental regulations.
10 MPH Speed Limit for Cars and Bikes on Crystal Springs at Polhemus
Thank you!
Wednesday, June 10, 2009
Controlled Blast Scheduled for North Shaft on Thursday, June 11
New Photos of Controlled Blasting and Muck Processing
Photo 1 - Crews lowering the blast cover on top of the South Shaft in preparation for a controlled detonation.
Photo 2 - a controlled detonation. All indicators for vibration, noise and air particulates are below the thresholds and are measured constantly.
Photo 3 - After the detonation, rock and earth (called muck) are removed from the shaft using the crane.
Monday, June 8, 2009
Controlled Blasting to Continue at South Shaft
Controlled Blasting Begins June 9th at North Shaft
Controlled blasting will begin as early as Tuesday, June 9th and will continue for several days each week until the contractor reaches necessary depth.
Controlled blasting can take place between 7am and 6pm Monday through Friday. All safety and noise control measures are in effect and the work is performed in accordance with California Occupational Safety and Health (OSHA) and environmental regulations. Neighbors may notice some noise and/or vibration during the controlled blasting.
If you would like to receive regular EMAIL or PHONE notifications of when controlled blasting will take place, please send an email to newcstunnel@sfwater.org or call 650-212-0165 and provide your email, phone, name and address by June 22nd. Blast schedules will also be posted on our Community Blog.
Friday, May 29, 2009
Pre-Construction Surveys along North Shaft
The controlled blasting that is taking place at the south shaft will move to the north shaft by mid-June.
Neighborhood Coffee: Save the date, Wednesday, June 24, 9 to 10 am. Members of the project team will be at Starbucks Coffee in the Crystal Springs Shopping Center to update you on the progress of the project and answer your questions. We invite you join us for a cup of coffee. Check back for details.
Wednesday, May 27, 2009
Controlled Blasting at South Shaft Runs Smoothly
Friday, May 8, 2009
Pre-Construction Surveys
Friday, May 1, 2009
A Bird's Eye View (Helicopter)
Wednesday, April 22, 2009
Baden and San Pedro Water System Upgrades
• West Orange Avenue and El Camino Real in South San Francisco
• B Street and Junipero Serra in Daly City
The work will improve the reliability of the regional water system, and reduce vulnerability and damage in the event of a major earthquake. The project will also provide greater operational flexibility to optimize the water delivery system to the City and County of San Francisco.
South San Francisco:
Monday to Friday: 8:00 am-5:00 pm.
Duration: May 2009 –Winter 2011
Daly City:
Monday to Friday: 7:00 am -5:00 pm
Duration: May 2009 – Winter 2010
Construction noise from heavy equipment and truck traffic can be expected and will be monitored. A noise reducing fence will be installed along the western and southern project boundaries, along West Orange and El Camino Real in South San Francisco.
Friday, April 17, 2009
Ground Breaking Event A Success!
KTVU News (Video), 4/17/09 SAN MATEO: Upgrade Of Hetch Hetchy Pipe System Gets Underway
KCBS News (Radio), 4/16/09 New Quake-Proof Pipeline to Deliver H2O to the Bay Area
SF Chronicle (Blog), 4/16/09 Tunnel time
Thursday, April 16, 2009
SFPUC, San Mateo County Officials Break Ground on New Tunnel Critical to Protecting Regional Water Supply After Major Earthquake
Excavation of a major new tunnel key to the reliable delivery of water to San Mateo County and San Francisco following a major earthquake began today in San Mateo County.San Francisco Public Utilities Commission (SFPUC) and San Mateo County Officials joined local neighbors to initiate the New Crystal Springs Bypass Tunnel groundbreaking two days before the 103rd anniversary of the 1906 Great Earthquake and Fire.
To view the press release, click the link below.
Wednesday, April 15, 2009
Temporary Traffic Changes in Effect
Friday, April 3, 2009
Temporary traffic impacts on Crystal Springs Road
Wednesday, March 25, 2009
Cyclists in the Area?
Friday, March 20, 2009
Join San Francisco Water on Facebook and Twitter!
To get your own stainless steel bottle, join us on Facebook during the week of March 22nd-29th by becoming a FAN of San Francisco Water on Facebook at http://tinyurl.com/d3zxj5. (Log-in to your personal facebook account to view page).
The San Francisco Water Facebook page will be regularly updated with new photos, interesting videos, drought updates, water and energy conservation tips and more.
The first 1,000 San Francisco residents who become fans of San Francisco Water will be eligible to pick up a stainless steel water bottle after March 29. Pick up details will be announced on Facebook. Please help us spread the word by sending this to your friends and colleagues! Invite your network to join us on Facebook and Twitter.
Follow us on Twitter for more great SFPUC news. http://twitter.com/SFWater
Monday, March 16, 2009
Groundwater Treatment Facility, Where and Why

As a reminder, SFPUC does not dictate means and methods the contractor should use. In this case, the contractor’s site layout resulted in the current upper level location of the water containment structures. The level of water in the treatment ponds will depend on the rate of inflow into project excavations and the time required for treatment prior to discharge. Of course, they will be removed at the end of the project.
Friday, March 13, 2009
Groundwater Test Site Under Construction

Thursday, March 12, 2009
Answers to Your Questions
Monday, March 2, 2009
View of the construction from your neighbor

Thursday, February 26, 2009
Construction Update

Inclinometers measure ground movement, they are being installed to measure the impact of construction activity on the slope. Look for the white drill rigs at the construction site.







