Friday, March 10, 2017

Historic Unfailing Dam Ready for Next 130 Years



                                          Lower Crystal Springs Dam after the 1906 Quake

It was built to last. The 1888 Lower Crystal Springs Dam, situated next to the San Andreas Fault,  survived two major earthquakes—the great earthquake of 1906 and the Loma Prieta in 1989—with no damage.  A critical recent upgrade plus our vigilant 24/7 operation ensure that the historic 175-foot-high dam is able to safely contain Crystal Springs Reservoir drinking water even in a year of record rainfall.

The main upgrade under the Water System Improvement Program was the widening of the spillway—an emergency device for the safe release of water during heavy rains—on top of the dam. The new expanse gives us the ability to release 2.5 times more water than before—if necessary. But again, a spillway is an emergency feature---and one that we haven’t had to use for decades, according to SFPUC Local-Regional Water System Manager David Briggs. 

The real safeguard is the day-to-day monitoring, anticipating and adjusting by our system operators.  They open valves to release controlled amounts of water into San Mateo Creek, and divert water northward to San Andreas Reservoir (at left), on to the Harry Tracy Water Treatment Plant (below), and then to customers. They continually forecast the anticipated amount of rain and runoff into the reservoir and assess that inflow’s impacts on reservoir level.  As needed, our operators will  release controlled amounts of water from the dam—but always taking into account the timing of high tides coming up the creek from the bay.   

We’ve been releasing water from the reservoir this way all winter, and have not come close to spilling water over the dam. 

The San Mateo Daily Journal talked with Briggs a couple of weeks ago.  You can read more on what he had to say about the safety of historic Crystal Springs Dam and our regulation of the water system here

Thursday, July 21, 2016

Peninsula Pipeline Project Receives Top Project Award!

San Andreas Pipeline No. 3 installation in San Bruno

Water & Wastes Digest selected the Peninsula Pipeline Seismic Upgrade (PPSU) Project as one of their Top Projects for 2016! Congrats PPSU project team, hopefully this is the first of many awards!

The PPSU project repaired and replaced several sections of water delivery pipelines in northern San Mateo County, to ensure these critical pipelines can withstand a major earthquake. This project completed all WSIP work in February 2016.

For more information about this project, visit www.sfwater.org/PPSU. 

Thursday, June 30, 2016

Happy Fourth of July!



On behalf of all of us here at the San Francisco Public Utilities Commission, we want to wish you a happy and enjoyable Independence Day!

As you prepare for the holiday weekend, we want to take this opportunity to update you on our holiday schedules for two important construction projects in the Peninsula.

Bioregional Habitat Restoration on the Peninsula:

  • Sawyer Camp Trail will be completely open starting the morning of Saturday, July 2 through the entire month of July.  
  • The partial trail closure will be back in place starting Monday, August 1 it the same location for ongoing habitat restoration.

Regional Groundwater Storage & Recovery (GSR) Project: 

  • No construction activity at any of the sites on Monday, July 4 in honor of the holiday
  • Normal construction will resume on Tuesday, July 5


Friday, May 20, 2016

WSIP Update on Repairing and Upgrading Your Water Infrastructure!



It’s Infrastructure Week and here at the San Francisco Public Utilities Commission (SFPUC) we have been implementing the Water System Improvement Program (WSIP), a $4.8 billion multi-year capital improvement program, to repair and upgrade our regional and local water system infrastructure to ensure the SFPUC can continue to supply reliable water to 2.6 million people in four Bay Area counties, especially after a major earthquake. 

Check out what the WSIP has been up to over the last year. 

Remember #infrastructurematters!

Friday, March 18, 2016

Construction Update: Lane Closure on Colma Boulevard Begins March 18

The SFPUC’s Regional Groundwater Storage & Recovery Project is making great progress in the Peninsula! This week the project team began installing an eight-inch diameter pipeline along Colma Boulevard in the Town of Colma. Once the Project is complete, this pipeline will connect our regional water customers with a water supply that can be used during a drought or other emergency.

During pipeline construction, one lane on Colma Boulevard will be closed (just west of El Camino Real) from 8 a.m. to 4 p.m. Monday through Friday. One lane of traffic will be maintained in each direction at all times.
  • Pipeline construction will begin as early as Friday, March 18 and will last approximately two weeks. 
  • Two construction message boards are posted on Colma Boulevard to notify traffic about upcoming lane closures.
  • The Project is sensitive to traffic during services along Colma Boulevard and will adjust operations, if needed
Above is an example of what pipeline installation work looks like on Colma Boulevard.

Friday, March 11, 2016

Time to Spring Forward!


It is starting to look a lot like spring on the Peninsula. One of our team members snapped this picture of some Golden Poppies from the Peninsula Pipeline Seismic Upgrade project site in South San Francisco. In addition, it is time to spring forward with Daylight savings time starting this Sunday, March 13, 2016. Don’t forget to turn your clocks forward one hour for more light in the evening and a later sunrise! Hello Spring!

Thursday, February 18, 2016

Capturing Construction in Photos


To our construction teams, Robin is a familiar face who frequently visits the active construction sites to shoot some candid photos of construction and our hard workers. Little did we  know that Robin not only works to document the construction progress but she gains much deserved national recognition while she is at it. For the Water System Improvement Program (WSIP), Robin’s photo of the New Irvington Tunnel Project made the Top Ten for the Engineering News Record (ENR) 2015 Year in Construction Photo Contest. This is a prestigious international construction photography competition, and we are extremely proud that Robin’s photo of our own tunnel was a winner!



About Robin
Robin Scheswohl moved to the Bay Area in 2003 from Philadelphia, PA where she studied photography and later worked with corporate and wedding photographers. She’s been with the SFPUC since 2007, working in the Construction Management Bureau and the Engineering Archives. She is responsible for cataloging and preserving thousands of historic images dating back to the 19th century, as well as documenting the Water System Improvement Program (WSIP) construction projects. SFPUC Engineering Archives Photography has curated public exhibits at City Hall, at the San Francisco International Airport, and the SF American Institute of Architects (AIA) Headquarters. The images are used extensively by the SFPUC and appear in books, periodicals, environmental and engineering studies.

Here is Robin filming at the Bay Tunnel, which is the first tunnel constructed under San Francisco Bay.  Congratulations, Robin!

Tuesday, February 16, 2016

Construction Activities Resume

 
Construction activities for the Regional Groundwater Storage & Recovery (GSR) and Peninsula Pipeline Seismic Upgrade (PPSU) projects will resume today, February 16, after observing the President's Day Holiday.

Friday, July 10, 2015

Neighbors Toured Newly Completed Harry Tracy Water Treatment Plant Upgrades

What better way to meet your neighbors than over coffee, bagels, and water treatment? On the last Saturday in June, more than 50 of our neighbors around the newly-upgraded Harry Tracy Water Treatment Plant accepted our invitation to do just that. The Plant has been under construction for the past four years in order to complete critical seismic and system upgrades as well as build an 11-million-gallon treated water reservoir on the site. It was our chance to show our patient neighbors what the fuss was about, and to say thank you.

Neighbors enjoy the view from the top of the newly completed Treated Water Reservoir.

The Plant treats drinking water that is stored in the Crystal Springs and San Andreas Reservoirs on the Peninsula before delivering it to communities in San Mateo and San Francisco counties. The upgraded Plant can now provide up to 140 million gallons of water per day for 60 days within 24 hours after a major earthquake to the almost 1 million people that it serves.

Project Construction Manger Ryan Cayabyab, Project Manager Calvin Huey, and plant operators Tim Kennedy and Jim Myint showed our guests around the plant. They explained how water is treated at the plant, and highlighted the new features recently installed as part of construction. Check out this time lapse to get a sense of the scale of the project.

The completion of the project is a huge milestone for the Water System Improvement Program (WSIP) and a critical component of a consistent, reliable and high-quality drinking water supply in the Bay Area.

We enjoyed meeting our delightful neighbors, and we look forward to seeing you all around the neighborhood.


A map of the upgrades completed during the Harry Tracy Water Treatment Plant Long-Term Improvements Project.

Friday, May 22, 2015

GSR Project Pipeline Construction Ramping-up in Daly City and Colma

The Regional Groundwater Storage and Recovery (GSR) Project will ramp-up pipeline construction activities inside the San Francisco Public Utilities Commission’s (SFPUC)’s right of way in Daly City and Colma next week.   
 
Serra Bowl Site in Daly City
  • The contractor will begin pipeline installation activities on Tuesday, May 26 which will increase activity at this site.
  • Permitted construction hours are currently Monday through Friday from 7 a.m. to 5 p.m.
  • Expect to see more construction vehicles, pipeline stored at the site and trenches to install the new pipeline. Also there may be some dust and noise associated with construction activities.

Colma Boulevard Site in Colma
  • The contractor will begin pipeline installation activities on Tuesday, May 26 which will increase activity at this site.
  • Permitted construction hours are currently Monday through Sunday from 7 a.m. to 5 p.m.
  • Expect to see more construction vehicles, pipeline stored at the site and trenches to install the new pipeline. Also there may be some dust and noise associated with construction activities.
 
For more information about the GSR Project, please be sure to subscribe to this blog. Visit sfwater.org/GSR or by calling us at (866) 973-1476.
 

 
 
 

Tuesday, March 10, 2015

Pipeline Construction South of Whitman Way Begins This Week

This week the PPSU project contractor, Ranger Pipelines, Inc., will start pipeline removal and replace approximately 1,100 feet of aged pipe inside the San Francisco Public Utilities Commission’s right-of-way south of Whitman Way and north of the San Bruno Chinese Church in San Bruno. 

Permitted construction hours are Monday through Friday from 7 a.m. to 7 p.m. and Saturday from 9 a.m. to 6 p.m. Construction activities at this location are expected to last through summer 2015. During these activities, please keep an eye out for intermittent sidewalk and lane closures along Whitman Way.


Pipeline construction and related activities will occur 
in the outlined areas pictured here.

What is the PPSU Project? 
The PPSU project includes the seismic upgrade of three Hetch Hetchy regional water delivery pipelines located in Northern San Mateo County. This project will ensure the pipelines can continue to deliver water to customers after an emergency.

Questions?
For more information, please call the 24-hour answering service at 866-973-1476, or subscribe to this project blog.

Friday, February 27, 2015

PPSU Pipeline Construction Begins in Shelter Creek Condominiums Next Week


The region outlined above indicates where construction activities
are occurring inside Shelter Creek Condominiums.


On Monday, March 2 the PPSU project contractor, Ranger Pipelines, Inc., will start pipeline removal and replace approximately 200 feet of aged pipe inside Shelter Creek Condominiums within the San Francisco Public Utilities Commission’s right-of-way. The contractor will also begin delivering and staging pipe on Monday, March 2.

Permitted construction hours are Monday through Friday from 8 a.m. to 5 p.m. and Saturdays from 9 a.m. to 5 p.m. on an as-needed basis. Construction activities inside Shelter Creek Condominiums are expected to last through summer 2015. The contractor has implemented a noise monitoring plan, vibration monitoring points and sound walls to minimize construction impacts.

During daytime activities, Shelter Creek Lane inside Shelter Creek Condominiums, depicted in the visual above, will be closed to vehicle traffic. All daytime traffic accessing Garage 4 and residents of Buildings 3, 4 and 5 will be rerouted via Whitman Way. Garage 3 residents will not be affected. At nighttime, the contractor will reopen Shelter Creek Lane to traffic.

The PPSU project includes the seismic upgrades of three Hetch Hetchy regional water delivery pipelines located in Northern San Mateo County. This project will ensure the pipelines can continue to deliver water to customers after an emergency.


For more information or if you have questions, please subscribe to this blog or call (866) 973-1476.

Friday, February 20, 2015

PPSU Pipeline Deliveries Begin in San Bruno Next Week!

On Wednesday, February 25, the PPSU project contractor, Ranger Pipelines, Inc., will begin delivering and staging pipeline materials along the SFPUC’s right of way south of Whitman Way in San Bruno. 

Permitted construction hours are currently Monday through Friday from 7 a.m. to 7 p.m. and Saturday from 9 a.m. to 6 p.m. Construction activities at this location are expected to last through summer 2015. During these activities, please keep an eye out for intermittent sidewalk and lane closures along Whitman Way. 


Pipeline deliveries in San Bruno will be similar to the activity shown above.

The PPSU project includes the seismic upgrades of three Hetch Hetchy regional water delivery pipelines located in Northern San Mateo County. This project will ensure the pipelines can continue to deliver water to customers after an emergency. 


Questions?
For more information, please call the 24-hour answering service at 866-973-1476, or subscribe to this blog.

Friday, January 23, 2015

WSIP Recognizes Construction Project Teams for 7 Million Safe Work Hours

The construction teams working on Water System Improvement Program (WSIP) projects recently achieved a huge and important milestone. Between April 2009 and October 2014, these project teams performed 7 million hours of work on major construction projects, without a single major injury or incident. SFPUC representatives acknowledged this with a formal presentation of a certificate to the active construction management and contractor teams in December.

The WSIP projects have significantly lower rates of recordable injuries and lost work time compared to the national industry averages. The safety successes are a result of a robust safety program that has been embraced by the construction management teams as well as the project contractors. This milestone is evidence of the project teams’ outstanding commitment to the Think Safety, Work Safely approach, ensuring the program’s construction sites are safe places to work.

Harry Tracy Water Treatment Plant Project: SFPUC Team and Kiewit Infrastructure West

Peninsula Pipeline Seismic Upgrade Project: SFPUC Team and Ranger Pipelines, Inc.


Thursday, January 22, 2015

PPSU Construction Activities Kick-off In Shelter Creek Condominiums This Week


The region outlined above indicates where construction activities inside 
Shelter Creek Condominiums will occur.

This week the PPSU project contractor, Ranger Pipelines, Inc., started construction activities inside the San Francisco Public Utilities Commission’s (SFPUC)’s right of way in Shelter Creek Condominiums. The contractor started site clearing within the right of way, setting up the construction staging areas, installing construction fences and installing shoring along the SFPUC right of way to prepare for pipeline construction that will begin in February.

Permitted construction hours are currently Monday through Friday from 8 a.m. to 5 p.m. and Saturdays from 9 a.m. to 5 p.m. on an as-needed basis. Construction activities inside Shelter Creek Condominiums are expected to last through summer 2015.

During daytime activities, Shelter Creek Lane inside Shelter Creek Condominiums, depicted in the visual above, will be closed to vehicle traffic. All daytime traffic accessing Garage 4 and residents of Buildings 3, 4 and 5 may be rerouted via Whitman Way. Garage 3 residents will not be affected. At nighttime, the contractor will reopen one lane to traffic on Shelter Creek Lane and will implement temporary signals to regulate the flow of traffic.

The PPSU project includes the seismic upgrades of three Hetch Hetchy regional water delivery pipelines located in Northern San Mateo County. This project will ensure the pipelines can continue to deliver water to customers after an emergency.

PPSU CONTACT INFORMATION:
· 24-hour Answering Service - 866-973-1476

· Subscribe to this project blog for construction updates.


Wednesday, January 14, 2015

PPSU Construction Begins to Ramp Up in Colma

This week the project contractor, Ranger Pipelines, Inc. will begin delivering and staging pipeline materials at the Colma site. Pipeline deliveries will occur Monday through Friday from 7 a.m. to 7 p.m. These pipeline deliveries are expected to last through the end of the week. During construction related activities, please keep an eye out for intermittent lane closures and traffic changes on Collins Avenue during construction.

Pipeline deliveries in Colma will be similar to the activity shown above.

On Monday, January 19, Ranger Pipelines, Inc. will begin removing and replacing approximately 700 feet of aged pipeline at the Colma site behind the Khol’s department store between Serramonte Boulevard and Collins Avenue within the SFPUC’s right-of-way. Permitted construction hours are Monday through Friday from 7 a.m. to 7 p.m. Pipeline construction and site restoration activities are expected to last through April 2015. The contractor will work to minimize noise, dust and traffic impacts, but some disruptions are expected due to the nature of construction.

The PPSU project includes seismically upgrading three Hetch Hetchy regional water delivery pipelines located in Northern San Mateo County. This project will ensure the pipelines can continue to deliver water to customers after an emergency. For more information, please subscribe to this blog to receive project updates or call (866) 973-1476.

Friday, January 9, 2015

South San Francisco Construction Update

Baden Valve Lot Construction 

On Monday, January 12, the PPSU project contractor, Ranger Pipelines, Inc., will begin replacing three critical valves within the San Francisco Public Utilities Commission (SFPUC)’s right of way in South San Francisco between Southwood Drive and West Orange Avenue.

These valves are critical to the Hetch Hetchy Regional Water System in the Peninsula. As a result, the contractor must replace all three valves in five days in order to put them back into operation by Friday, January 16.

With this limited construction time frame, the contractor will work 24-hour shifts for this five day period. To minimize noise impacts, the contractor will refrain from using loud equipment and back-up alarms after 8 p.m. 24-hour noise monitoring will occur to ensure noise does not exceed the City of South San Francisco’s noise ordinance and construction lighting will be pointed away from homes.


Construction project limits near Garden Chapel Funeral Home in South San Francisco.

Westborough Boulevard & Orange Avenue Construction

The project contractor, Ranger Pipelines, Inc., has completed construction of the new tunnel shafts under Westborough Boulevard. The SFPUC’s water pipelines will be taken out of service on Saturday, January 10 and the contractor will begin installing the new pipeline under Westborough Boulevard. Permitted construction hours are Monday through Friday from 8 a.m. to 8 p.m. and Saturday from 9 a.m. to 8 p.m. These construction activities are expected to last through March 2015. 


Construction project limits at Westborough Boulevard and Orange Avenue in South San Francisco.

What is the PPSU project?
The PPSU project includes the seismic upgrade of three Hetch Hetchy regional water delivery pipelines located in Northern San Mateo County. This project will ensure the pipelines can continue to deliver water to customers after an emergency.

For more information, please subscribe to this blog to receive project updates or call (866) 973-1476.

Monday, December 29, 2014

Night Work in South San Francisco Begins in January

On Monday, January 12, the PPSU project contractor, Ranger Pipelines, Inc., will begin replacing three critical valves within the San Francisco Public Utilities Commission (SFPUC)’s right of way in South San Francisco between Southwood Drive and West Orange Avenue.

These valves are a critical to the Hetch Hetchy Regional Water System in the Peninsula. As a result, the contractor must replace all three valves in five days in order to put them back into operation by Friday, January 16.

With this limited construction time frame, the contractor will work 24-hour shifts for this five day period. To minimize noise impacts, the contractor will refrain from using loud equipment and back-up alarms after 8 p.m. 24-hour noise monitoring will occur to ensure noise does not exceed the City of South San Francisco’s noise ordinance and construction lighting will be pointed away from homes.

The PPSU project includes the seismic upgrade of three Hetch Hetchy regional water delivery pipelines located in Northern San Mateo County. This project will ensure the pipelines can continue to deliver water to customers after an emergency.

For more information, please call the 24-hour answering service at 866-973-1476, or subscribe to this blog. 

Outlined above are the construction limits where 24-hour shifts will occur Monday, January 12 through Friday, January 16. The green triangles indicate the location for valve replacement inside the work area.

Thursday, December 4, 2014

The PPSU project contractor, Ranger Pipelines, Inc., will begin construction activities on Monday, December 8 within the San Francisco Public Utilities Commission’s right of way inside Shelter Creek Condominiums next week. The contractor will begin this work by removing debris, trees, and shrubs from the work area. Crews will also be relocating a water and electrical line outside of the work area, installing temporary lighting, and installing construction signage.

The PPSU project team is working closely with the Shelter Creek Condominium Board to minimize impacts during work for this project. Construction activities inside the Shelter Creek Condominium work area are currently planned for Monday through Friday from 8 a.m. to 5 p.m., but in case of an emergency, night and work may be needed. Construction activities at this location will occur in two phases and expected to last through summer 2015.

The PPSU project includes seismically upgrading three Hetch Hetchy regional water delivery pipelines located in Northern San Mateo County. This project will ensure the pipelines can continue to deliver water to customers after an emergency. For more information, please call the 24-hour answering service at 866-973-1476, or subscribe to this blog to receive project updates.



Construction activities inside Shelter Creek Condominiums will begin Monday, December 8.