Friday, May 20, 2016

WSIP Update on Repairing and Upgrading Your Water Infrastructure!



It’s Infrastructure Week and here at the San Francisco Public Utilities Commission (SFPUC) we have been implementing the Water System Improvement Program (WSIP), a $4.8 billion multi-year capital improvement program, to repair and upgrade our regional and local water system infrastructure to ensure the SFPUC can continue to supply reliable water to 2.6 million people in four Bay Area counties, especially after a major earthquake. 

Check out what the WSIP has been up to over the last year. 

Remember #infrastructurematters!

Wednesday, August 26, 2015

PPSU Project Will Close Whitman Way for Pipeline Work

Beginning as early as Thursday, September 3, Whitman Way will be closed between Shelter Creek Lane and Courtland Drive from 9 a.m. to 3:30 p.m. for back filling and repaving across Whitman Way as part of the Peninsula Pipeline Seismic Upgrade (PPSU) Project. Whitman Way will reopen at the end of each work day at 3:30 p.m. 

Whitman Way will be closed during the following time periods: 

· Thursday, September 3 and Friday, September 4
· Tuesday, September 8 through Friday, September 11 
· Monday, September 14 through Friday, September 18

During this closure, all traffic will be detoured to San Bruno Avenue via Shelter Creek Lane, Madison Avenue and Crestmoor Drive. For more information and updates about this closure, please call the 24-hour answering service at (866) 973-1476 or subscribe to this blog to receive project updates.

The full closure of Whitman Way anticipates starting as early as Thursday, September 3 inside the orange rectangle pictured above.

The PPSU project includes seismically upgrading three Hetch Hetchy regional water delivery pipelines located in Northern San Mateo County. This project will ensure the pipelines can continue to deliver water to customers after an emergency. 

Tuesday, March 10, 2015

Pipeline Construction South of Whitman Way Begins This Week

This week the PPSU project contractor, Ranger Pipelines, Inc., will start pipeline removal and replace approximately 1,100 feet of aged pipe inside the San Francisco Public Utilities Commission’s right-of-way south of Whitman Way and north of the San Bruno Chinese Church in San Bruno. 

Permitted construction hours are Monday through Friday from 7 a.m. to 7 p.m. and Saturday from 9 a.m. to 6 p.m. Construction activities at this location are expected to last through summer 2015. During these activities, please keep an eye out for intermittent sidewalk and lane closures along Whitman Way.


Pipeline construction and related activities will occur 
in the outlined areas pictured here.

What is the PPSU Project? 
The PPSU project includes the seismic upgrade of three Hetch Hetchy regional water delivery pipelines located in Northern San Mateo County. This project will ensure the pipelines can continue to deliver water to customers after an emergency.

Questions?
For more information, please call the 24-hour answering service at 866-973-1476, or subscribe to this project blog.

Thursday, January 22, 2015

PPSU Construction Activities Kick-off In Shelter Creek Condominiums This Week


The region outlined above indicates where construction activities inside 
Shelter Creek Condominiums will occur.

This week the PPSU project contractor, Ranger Pipelines, Inc., started construction activities inside the San Francisco Public Utilities Commission’s (SFPUC)’s right of way in Shelter Creek Condominiums. The contractor started site clearing within the right of way, setting up the construction staging areas, installing construction fences and installing shoring along the SFPUC right of way to prepare for pipeline construction that will begin in February.

Permitted construction hours are currently Monday through Friday from 8 a.m. to 5 p.m. and Saturdays from 9 a.m. to 5 p.m. on an as-needed basis. Construction activities inside Shelter Creek Condominiums are expected to last through summer 2015.

During daytime activities, Shelter Creek Lane inside Shelter Creek Condominiums, depicted in the visual above, will be closed to vehicle traffic. All daytime traffic accessing Garage 4 and residents of Buildings 3, 4 and 5 may be rerouted via Whitman Way. Garage 3 residents will not be affected. At nighttime, the contractor will reopen one lane to traffic on Shelter Creek Lane and will implement temporary signals to regulate the flow of traffic.

The PPSU project includes the seismic upgrades of three Hetch Hetchy regional water delivery pipelines located in Northern San Mateo County. This project will ensure the pipelines can continue to deliver water to customers after an emergency.

PPSU CONTACT INFORMATION:
· 24-hour Answering Service - 866-973-1476

· Subscribe to this project blog for construction updates.


Wednesday, January 14, 2015

PPSU Construction Begins to Ramp Up in Colma

This week the project contractor, Ranger Pipelines, Inc. will begin delivering and staging pipeline materials at the Colma site. Pipeline deliveries will occur Monday through Friday from 7 a.m. to 7 p.m. These pipeline deliveries are expected to last through the end of the week. During construction related activities, please keep an eye out for intermittent lane closures and traffic changes on Collins Avenue during construction.

Pipeline deliveries in Colma will be similar to the activity shown above.

On Monday, January 19, Ranger Pipelines, Inc. will begin removing and replacing approximately 700 feet of aged pipeline at the Colma site behind the Khol’s department store between Serramonte Boulevard and Collins Avenue within the SFPUC’s right-of-way. Permitted construction hours are Monday through Friday from 7 a.m. to 7 p.m. Pipeline construction and site restoration activities are expected to last through April 2015. The contractor will work to minimize noise, dust and traffic impacts, but some disruptions are expected due to the nature of construction.

The PPSU project includes seismically upgrading three Hetch Hetchy regional water delivery pipelines located in Northern San Mateo County. This project will ensure the pipelines can continue to deliver water to customers after an emergency. For more information, please subscribe to this blog to receive project updates or call (866) 973-1476.

Friday, January 9, 2015

South San Francisco Construction Update

Baden Valve Lot Construction 

On Monday, January 12, the PPSU project contractor, Ranger Pipelines, Inc., will begin replacing three critical valves within the San Francisco Public Utilities Commission (SFPUC)’s right of way in South San Francisco between Southwood Drive and West Orange Avenue.

These valves are critical to the Hetch Hetchy Regional Water System in the Peninsula. As a result, the contractor must replace all three valves in five days in order to put them back into operation by Friday, January 16.

With this limited construction time frame, the contractor will work 24-hour shifts for this five day period. To minimize noise impacts, the contractor will refrain from using loud equipment and back-up alarms after 8 p.m. 24-hour noise monitoring will occur to ensure noise does not exceed the City of South San Francisco’s noise ordinance and construction lighting will be pointed away from homes.


Construction project limits near Garden Chapel Funeral Home in South San Francisco.

Westborough Boulevard & Orange Avenue Construction

The project contractor, Ranger Pipelines, Inc., has completed construction of the new tunnel shafts under Westborough Boulevard. The SFPUC’s water pipelines will be taken out of service on Saturday, January 10 and the contractor will begin installing the new pipeline under Westborough Boulevard. Permitted construction hours are Monday through Friday from 8 a.m. to 8 p.m. and Saturday from 9 a.m. to 8 p.m. These construction activities are expected to last through March 2015. 


Construction project limits at Westborough Boulevard and Orange Avenue in South San Francisco.

What is the PPSU project?
The PPSU project includes the seismic upgrade of three Hetch Hetchy regional water delivery pipelines located in Northern San Mateo County. This project will ensure the pipelines can continue to deliver water to customers after an emergency.

For more information, please subscribe to this blog to receive project updates or call (866) 973-1476.

Wednesday, June 25, 2014

WSIP’s Last Pipeline Project Begins August 2014!


The Peninsula Pipelines Seismic Upgrade (PPSU) is starting construction! The construction contract was awarded to Ranger Pipelines, Inc. Pre-construction work is already underway with construction activities scheduled to begin in August 2014.

The PPSU project consists of seismic upgrades to three critical water delivery pipelines in Northern San Mateo County. These upgrades are needed to ensure drinking water delivery to our customers following an earthquake. We will replace segments of the pipeline, open-trench construction, surface restoration and installing structural support within an existing tunnel.

The PPSU project spans six improvement components in four different cities on the San Francisco Peninsula within San Mateo County: Millbrae, South San Francisco, San Bruno and Colma. For more details, view the project fact sheet here.

This pipeline project is one of more than 80 water improvement projects that are part of the Hetch Hetchy Water System Improvement Program (WSIP). The PPSU project is the final pipeline replacement project in the WSIP program.

To kick off construction, the PPSU project team will host an open house event on Thursday, July 24 at the City of Millbrae Public Library (1 Library Avenue, Millbrae, CA, 94030). The public is invited to talk with the project team about upcoming construction activities between 5:30 p.m. and 7:30 p.m. To receive project updates, please subscribe to this blog or visit our project web page www.sfwater.org/PPSU.

Friday, June 20, 2014

The WSIP Turns 10!


This year the Water System Improvement Program (WSIP) turns 10! One of the largest infrastructure projects in the nation, the WSIP is repairing, replacing and upgrading our aging water infrastructure to ensure we can deliver water to customers following an earthquake. We’ve gotten a little nostalgic about how far we’ve come in the last 10 years, and we would like to share this video with you.



Now 80 percent complete, the WSIP has already provided increased reliability to the water supply for customers as a result of the completion of some of the program’s major projects. The program has created over 6 million construction craft hours to date, employing more than 11,000 workers since 2007. Nearly half of those workers live in our four-county service area.