Friday, April 29, 2016

Regional Groundwater Project Celebrates One Year in Construction

In April 2015, the Regional Groundwater Storage and Recovery project kicked off construction at the Linear Park site in South San Francisco. Only one year later, the project is more than 32 percent complete and overcoming construction challenges to reach the finish line.


Workers install steel rebar to prepare for the wall pours at the Linear Park well station in July 2015. On the right is the completed exterior of the Linear Park well station in March 2016.


In November 2015, the project started well drilling activities at the Treasure Island site in South San Francisco. The project completed drilling all wells apart of this contract in early 2016.


Construction crews finished installing new pipeline on South Spruce Avenue in South San Francisco in March 2016.

With these milestones successfully complete, the project team knows there is still a lot of work to be done before completion in October 2017.


Friday, October 16, 2015

Regional Groundwater Project Begins Construction Activities at Treasure Island RV Park Site

Beginning as early as this week, the San Francisco Public Utilities Commission’s (SFPUC) Groundwater Storage and Recovery project will begin construction activities. The scope of work includes drilling a new groundwater well that will be 590 feet deep, installing approximately 180 feet of pipeline and building a new well station adjacent to the Treasure Island RV Park in South San Francisco (please reference the map below for the exact location).

24-hour well drilling work will occur continuously for up to
one month inside the blue rectangle pictured above. 

The project anticipates well drilling will begin in October. Once this work begins, it will occur continuously for 24-hours a day for up to one month in duration. To minimize noise impacts, the contractor will monitor noise levels and install sound curtains with blankets to ensure the levels do not exceed the local noise ordinance. During night work, the contractor will rotate construction lighting to direct it away from homes near the well drilling work.

Questions?
For more information about this project, please call the 24-hour answering service at 866-973-1476, or visit the Project webpage at sfwater.org/GSR.

Friday, September 25, 2015

Regional Groundwater Project Begins Construction at Orchard Supply & Hardware Site Next Week

The San Francisco Public Utilities Commission’s Regional Groundwater Storage and Recovery (GSR) project anticipates starting construction on approximately Monday, September 28. Major construction activities will include drilling a new groundwater well to a depth of 440 feet deep, installing 790 feet of pipeline and building a new well station near the Orchard Hardware & Supply store in Millbrae. Once drilling begins, this activity will last 24-hours a day for up to one month.


24-hour well drilling work will occur continuously
for up to one month inside the blue rectangle pictured above. 

To minimize noise impacts, the contractor will monitor noise levels and install sound blankets to ensure it does not exceed the local noise ordinance. During night work, the contractor will rotate construction lighting to direct it away from homes near well drilling work.

Questions?
For more information about this project, please call the 24-hour answering service at (866) 973-1476, or visit the Project webpage at sfwater.org/GSR.

Friday, August 7, 2015

Construction Notice: Regional Groundwater Project to Begin 24-hour Well Drilling in Colma

On Monday, August 10, the San Francisco Public Utilities Commission's (SFPUC) Regional Groundwater Storage and Recovery (GSR) Project will begin preparing the Colma Boulevard site for construction activities. Beginning as early as Monday, August 17, the GSR Project will begin drilling a new groundwater well that will be 690 feet deep near Colma Boulevard in Colma. Please reference the map below for the exact location.

24-hour well drilling work near Colma Boulevard anticipates starting on  
Monday, August 17 inside the blue rectangle pictured above. 

Once well drilling begins, work will occur continuously for 24-hours a day for up to one month in duration. To minimize noise impacts, the contractor will monitor noise levels and install sound blankets to ensure the levels do not exceed the local noise ordinance.  During night work, the contractor will rotate construction lighting to direct it away from properties near well drilling activities. 

Tuesday, July 14, 2015

Regional Groundwater Storage & Recovery Project to Begin Drilling in South San Francisco

Beginning as early as Wednesday, July 15, the San Francisco Public Utilities Commission’s Regional Groundwater Storage and Recovery (GSR) project will begin drilling a new groundwater well to a depth of 620 feet deep at Garden Chapel Funeral Home in South San Francisco.


24-hour well drilling work will occur continuously for up to one month inside the blue rectangle pictured above. 


To minimize noise impacts, the contractor will monitor noise levels and install sound blankets to ensure it does not exceed the local noise ordinance. During night work, the contractor will rotate construction lighting to direct it away from homes near well drilling work. 

Questions?
For more information about this project, please call the 24-hour answering service at 866-973-1476, or visit the Project webpage at sfwater.org/GSR. 

Tuesday, July 7, 2015

New Interactive Map for Regional Groundwater Storage & Recovery Project

The Regional Groundwater Storage & Recovery (GSR) Project has multiple active sites across five cities: Daly City, South San Francisco, Millbrae, Colma and San Bruno. In an effort to keep you informed about construction activities, detours and other project updates associated with GSR Project’s 13 sites, we have developed a Geographic Information System (GIS) Map.

This GIS map will be located on the project webpage www.sfwater.org/GSR. The map will be updated regularly depending on construction activities. A a snapshot of the GIS map with functionality capabilities is below.




  • Click numbers 1 - 13 to review construction site information
  • Each site has a box that highlights current status, hours and upcoming work
  • The blue area illustrates the construction area limits associated with the site
  • Use the navigational + and - sign to zoom in and out of the GSR project map

Thursday, June 11, 2015

Regional GSR Project Begins Well Drilling Next Week

On Thursday, June 18, the San Francisco Public Utilities Commission’s Regional Groundwater Storage and Recovery (GSR) project will begin drilling a new groundwater well to a depth of 730 feet deep at Benjamin Franklin Intermediate School in Daly City.

24-hour well drilling work will occur continuously for up to one month. inside the blue rectangle pictured above. 

To minimize noise impacts, the contractor will monitor noise levels and install sound blankets to ensure it does not exceed the local noise ordinance. During night work, the contractor will rotate construction lighting to direct it away from homes near well drilling work. 

Questions?
For more information about this project, please call the 24-hour answering service at 866-973-1476, or visit the Project webpage at sfwater.org/GSR.