On Monday, August 10, the San Francisco Public
Utilities Commission's (SFPUC) Regional Groundwater Storage and Recovery (GSR)
Project will begin preparing the Colma Boulevard site for construction
activities. Beginning as early as Monday,
August 17, the GSR Project will begin drilling a new
groundwater well that will be 690 feet deep near Colma Boulevard in Colma.
Please reference the map below for the exact location.
24-hour
well drilling work near Colma Boulevard anticipates starting on
Monday,
August 17 inside the blue rectangle pictured
above.
Once well drilling begins, work
will occur continuously for
24-hours a day for up to one month in duration. To minimize
noise impacts, the contractor will monitor noise levels and install sound
blankets to ensure the levels do not exceed the local noise ordinance.
During night work, the contractor will rotate construction lighting to direct it
away from properties near well drilling activities.