Friday, September 25, 2015

Regional Groundwater Project Begins Construction at Orchard Supply & Hardware Site Next Week

The San Francisco Public Utilities Commission’s Regional Groundwater Storage and Recovery (GSR) project anticipates starting construction on approximately Monday, September 28. Major construction activities will include drilling a new groundwater well to a depth of 440 feet deep, installing 790 feet of pipeline and building a new well station near the Orchard Hardware & Supply store in Millbrae. Once drilling begins, this activity will last 24-hours a day for up to one month.


24-hour well drilling work will occur continuously
for up to one month inside the blue rectangle pictured above. 

To minimize noise impacts, the contractor will monitor noise levels and install sound blankets to ensure it does not exceed the local noise ordinance. During night work, the contractor will rotate construction lighting to direct it away from homes near well drilling work.

Questions?
For more information about this project, please call the 24-hour answering service at (866) 973-1476, or visit the Project webpage at sfwater.org/GSR.

Friday, September 11, 2015

Mobilization & Construction Activities Begin at Lake Merced Golf Club GSR Site

This week, the San Francisco Public Utilities Commission's (SFPUC) Regional Groundwater Storage and Recovery (GSR) Project started mobilization and construction activities to prepare for drilling a new groundwater well that will be 620 feet deep at Lake Merced Golf Club in Daly City (please reference the map on the back for the exact location).

Once well drilling begins, work will occur continuously. To minimize noise impacts, the contractor will monitor noise levels and install sound blankets to ensure the levels do not exceed the local noise ordinance. During night work, the contractor will rotate construction lighting to direct it away from homes near the well drilling work.


24-hour well drilling work at Lake Merced Golf Club anticipates starting 
next week inside the blue rectangle pictured above. 

Once well drilling begins, work will occur continuously for up to one month. To minimize noise impacts, the contractor will monitor noise levels and install sound blankets to ensure the levels do not exceed the local noise ordinance. During night work, the contractor will rotate construction lighting to direct it away from properties near well drilling activities.


For more information about the GSR Project, please be sure to subscribe to this blog, visit sfwater.org/GSR or by calling us at (866) 973-1476.