Night work on the new 78-inch treated water pipeline will continue at the plant through early September. This swing shift is currently scheduled Monday to Friday, 6 p.m. to 4 a.m.
Noise
monitors will take readings every night near the entrance to the plant on Crystal Springs Road to ensure compliance.
Inside the
new 11 million gallon Treated Water Reservoir, work will take place 24 hours a
day. Construction workers are coating the inside of the tank to make sure it is
sealed and water-tight. Neighbors are unlikely to hear noise from work inside
the reservoir tank.
Millbrae
Concrete
trucks are scheduled to use Millbrae’s
Helen Drive this Friday, August 1st
from 11 a.m. to 3 p.m. to enter the plant via the Helen Gate. Our neighbors on Helen Drive may notice a truck approximately every 20
minutes during those hours. Flaggers will be present to ensure safety.
Night work
on the Millbrae
side of the plant near Sycamore Drive is
expected to begin after Labor Day.
Please
subscribe to this blog (see right) to receive automatic email updates with
schedule and work hour details. You can also reach us 24 hours a day at (866)
973-1476.