No night work is currently
planned.
Through February 2015, our
Contractor will continue building a new road inside the plant that will improve
access for maintenance workers. All work is taking place inside the plant
property.
Through early January, a
small crew will also continue sandblasting and coating the new washwater tank
located near our Millbrae
neighbors on Sycamore Drive. In 2014 the
project team completed the construction of five new filters. This washwater
tank holds the water used to clean these filters during the filtration process.
Exterior work on the tank is scheduled for Monday, December 29 through
Wednesday, December 31.
The plant is now back in
operation and capable of treating water from the Crystal Springs Reservoir
System. The work was completed on schedule…just in time for the winter rains!
Please do not hesitate to
call us if you have any questions or concerns: (866) 973-1476.
No comments:
Post a Comment