Thursday, July 14, 2011

Construction Update: Polhemus Road Near Bunker Hill

Kiewit Infrastructure West, contractor for the Hetch Hetchy Regional Water System, will be utilizing water system property at the corner of Bunker Hill Rd and Polhemus Rd. for temporary construction storage over the next 3 months.

Starting within the next two weeks, there will be truck and hauling activity onto the site (accessing from Polhemus Rd. only). We expect this activity to last approximately one week once it begins. Trucks will be delivering and storing soil at the site while construction at Lower Crystal Springs Dam is ongoing. All soil storage will be covered and continually monitored to ensure dust and runoff does not occur.

Truck hauling hours: 8AM – 6PM
Duration: Truck activity for one week.

Questions?
Please call our 24-hour answering service at (866) 973-1476 or email peninsula@sfwater.org.

For details about the Lower Crystal Springs Dam project, subscribe to our website for project updates: www.sfwater.org/SCT.



Thursday, July 7, 2011

Harry Tracy Water Treatment Plant Upgrades

Starting July 7th, contractor, Kiewit Infrastructure West, Inc. will begin pile-driving activities at our Harry Tracy Water Treatment Plant (near 280 and Crystal Springs Road). This plant treats drinking water from the Crystal Springs Reservoir System (Upper and Lower Crystal Springs Reservoirs and San Andreas Lake) for delivery to northern San Mateo County and San Francisco.

Pile-driving is necessary to form the foundation of our new seismically upgraded treated water reservoir. The first phase of this activity is expected to last no longer than 3 weeks (approximately the end of July).

All work for this project will take place within our property.

Additional noise may be audible to adjacent areas during construction activity. Noise levels will be monitored and maintained within permitted limits.

Vibrations are not expected to impact adjacent areas.

Residents may see additional truck traffic along Crystal Springs Road, as materials are delivered and removed from the site.

Wednesday, June 29, 2011

Northern Section of Sawyer Camp Trail Closed on Wednesday night, June 29th through Friday, July 1st

A northern portion of Sawyer Camp Trail will be closed from the Hillcrest Gate entrance in Millbrae to the 4.5 mile marker beginning this Wednesday, June 29th at 5 p.m. The closure will be in effect through Friday, July 1st. When the trail reopens, please use caution as a metal plate will be located on the trail near the San Andreas Dam (approximately 1 mile south of the Hillcrest entrance).

The southern trailhead at Skyline Blvd. and Crystal Springs Rd. will be open as usual, but hikers will need to turn around by the 4.5 mile marker. No through traffic will be permitted. If you frequent the northern section of Sawyer Camp, you may have noticed lots of construction activity! Crews are seismically upgrading the Hetch Hetchy Regional Water System -- ongoing work in the Peninsula Watershed is to enhance the reliability of San Mateo County’s emergency water supply.

Additional closures planned in July not related to the construction project:

July 11th: Cal-Fire tentatively plans to do seasonal fire prevention on Monday morning July 11th, and may close the northern trailhead at the Hillcrest Gate for a few hours.

July 12th – 14th: San Mateo County Parks will close the entire trail for three days (Tuesday through Thursday) to do required seasonal maintenance.

Please subscribe for automatic updates on trail closures on the blog: www.sfwater.org/SCT

Tuesday, June 28, 2011

Workers Along Polhemus Road in San Mateo Starting June 29th

Starting on Wednesday, June 29th, the contractor for the New Crystal Springs Bypass Tunnel and Pipeline project will begin performing removal work on small devices, called piezometers, on some of the hillsides and shoulders along Polhemus Road in San Mateo. Several work trucks will also be in the area.

On Thursday, June 30th, work will take place on Polhemus Road near the retaining wall located near the intersection of Ascension Drive and will require traffic control. Neighbors in the area may experience temporary traffic delays.

Thank you for your patience as we complete this important water project.

Monday, June 20, 2011

Please do not drive on upper terrace of South Shaft site off Polhemus Road

The project team has noticed tire tracks on the upper terrace area of the New Crystal Springs Bypass Tunnel's South Shaft site off of Polhemus Road in San Mateo.

PLEASE do not drive cars, trucks, bicycles, etc on the upper terrace area/meadow area of the site. Driving on it will create issues for dust control and erosion. We have measures in place to reduce dust so it does not blow onto homes above.

This fall, we will be adding a native seed mixture to the upper terrace/meadow area.

Thank you for your patience and support as we complete this important water infrastructure project.

Thursday, May 26, 2011

Aqua Colored Soil Stabilizer added to NCSBT Meadow Area near Polhemus Rd in San Mateo


Is anyone wondering why the upper terrace/meadow/muck disposal area at the South Shaft construction site of the New Crystal Springs Bypass Tunnel (NCSBT) is now an aqua-blue/green color?

In order to help prevent erosion and to control dust, the contractor has added a soil stablizer in preparation for revegitation.

In late summer/early fall, the area will be seeded with natives grasses and plants.

Please note the color of the soil stabilizer will fade over time! We promise the color is only temporary.

Monday, May 23, 2011

Construction Update at Peninsula Watershed Reservoirs

Silt curtains to protect species and water quality
delivered to San Andreas Lake: May 10, 2011

Barge and Dive Boat Launching at San Andreas Lake:

Does the water level appear low to you at San Andreas Lake? It will continue to get slightly lower to accommodate upcoming underwater seismic improvements. You may also see our crew transporting large marine equipment near the trailhead to San Andreas Trail and the northern entrance to the Sawyer Camp Trail.

The construction team must use the Hillcrest Gate entrance for water craft and other large equipment, which may cause delays on Hillcrest Blvd. (near Skyline in Millbrae, just west of 280). Large deliveries are expected over the next couple of weeks, with work in the reservoir taking place all summer.

If you frequently access Sawyer Camp Trail from Millbrae’s northern trailhead, the trail will remain open! Follow us on Twitter for real-time updates about activities: http://www.Twitter.com/SawyerCampTrail.

Pulgas Water Temple Temporary Closure: