Wednesday, July 18, 2012

Harry Tracy Water Treatment Plant – July 19 Concrete Pour

The Harry Tracy project contractor will be pouring concrete on Thursday, July 19th beginning at 7 a.m.

Expect frequent concrete truck deliveries on Crystal Springs Road between 7 a.m. and noon. A total of 65 trips are anticipated through 6 p.m. A similar one-day pour is expected next week.

The work is part of the seismic improvement of the plant, which serves over 1 million customers in northern San Mateo and San Francisco counties.  Post a comment here or call us 24 hours a day (866) 973-1476 with any questions or concerns!


Friday, June 1, 2012

18-Day Road Closure: Crystal Springs Road between Polhemus and Skyline/Hwy 35

Crystal Springs Road between Polhemus and Skyline/Hwy 35, in unincorporated San Mateo County just south of the Town of Hillsborough, will be closed be for 18 consecutive days from Monday, June 11th to Friday, June 29th . The road closure is necessary to replace a regional water pipeline as part of the Crystal Springs Pipeline No. 2 project.  

The closure will be in effect for cars and other vehicles 24 hours a day, Monday through Sunday, from June 11 to June 29. Bicycles only will have through access on Sundays to Sawyer Camp Trail. The road will be closed for cyclists Monday to Saturday – including Saturdays June 16th and 23rd.

For updates, please subscribe (see right) or Follow us on Twitter: @sawyercamptrail.  

During the closure, cars will be detoured onto Hwy 280. Bicycles will be detoured to Hillsborough city streets.  (Click on map to enlarge)

Bicycle Detour
From Hwy 35:
· Take Hayne Road under 280
· Turn Right on Black Mountain
· Continue on Black Mountain
· Turn Right on W. Santa Inez
· Continue on Brentwood
· Turn Right on El Cerrito
· Turn Right on Crystal Springs

From Polhemus Road:
· Take Crystal Springs Road (North)
· Turn Left on El Cerrito
· Turn Left on Hayne Road, continue under 280

Motorist Detour Information
From 280:
· Use 280 South to Bunker Hill
· Exit Bunker Hill, continue East to Polhemus Road
· Turn left on Polhemus Road

From Polhemus Road:
· Go South on Polhemus Road
· Turn right (East) on Bunker Hill
· Take 280 North to Hayne/Black Mountain Exit

 

Look How Far the Water System Improvement Program Has Come

The Water System Improvement Program (WSIP) is $4.6-billion of infrastructure upgrades, including more than 80 projects located in six Bay Area counties to ensure the highest quality drinking water and a reliable water supply to customers following an earthquake. These seismic improvements include dams, tunnels, pipelines, treatment plants and many more facilities that serve 2.6 million Bay Area customers. 2011 marked the start of the WSIP’s most active construction year to date. As of March 31, 2012, 55 out of 81 local and regional projects have been completed. All WSIP projects are forecasted to be complete in 2016. To view our progress and learn more about our water system, check out our video of water system improvements in your area here: http://www.youtube.com/watch?v=5qwqUcPIOyM&feature=youtu.be 



Tuesday, May 29, 2012

Night Work at the Harry Tracy Water Treatment Plant Begins May 29th

Night work at Harry Tracy begins on Tuesday, May 29th and will continue throughout the month of June. The temporary night shift work announced earlier in May was postponed to the day after Memorial Day. Work hours are 5 p.m. to 1 a.m.  Crews will be excavating a pipe in the main road within the plant as part of the seismic upgrade of the water system. The work on the plant’s main road must be done at night so that daily Operations and regular construction activities may continue during the day.

Our contractor will monitor noise each night to ensure levels comply with local ordinances. All work will take place within the plant and no haul trucks will be on the public roadways during the night shift. Night lighting will be confined to the specific work area. 

We apologize in advance for any disturbance and invite you to call our 24-hour phone line at (866) 973-1476.

Monday, May 14, 2012

Night Work Postponed at Harry Tracy

The night shift work previously planned for this week at Harry Tracy has been postponed to late May and early June. Construction work at the plant will finish by 6 p.m. this week.     

Please subscribe (see right) for automatic email updates about the construction at the Harry Tracy Water Treatment Plant.  Also, you can post your thoughts and suggestions to help make this project as neighbor friendly as possible.  

If you have immediate questions, please call us at (866) 973-1476!

Friday, May 11, 2012

Harry Tracy Construction Update

Night work at the Harry Tracy Water Treatment Plant will take place next Monday, May 14th through Friday, May 18th.

Work hours for the temporary night shift are 5 p.m. to 1 a.m.  Crews will be excavating a pipe in the main road within the plant as part of the seismic upgrade of the water system. The work on the plant’s main road must be done at night so that daily Operations and regular construction activities may continue during the day.

Our contractor will monitor noise each night to ensure levels comply with local ordinances. All work will take place within the plant and no haul trucks will be on the public roadways during the night shift. Night lighting will be confined to the specific work area. 

We apologize in advance for any disturbance and invite you to call our 24-hour phone line at (866) 973-1476.

Thursday, May 3, 2012

Harry Tracy Water Treatment Plant Update

Pile driving for the foundation of the new 11 million gallon Treated Water Reservoir will begin Monday, May 7th and is expected to take two weeks, weekdays only.

Saturday work is required for the next three Saturdays to keep critical activities on schedule. The work will take place inside the plant only. Approximately 20 truck trips are anticipated on Crystal Springs Road each Saturday (May 5th, May 12th and May 19th) to bring backfill to the site. The trucks will arrive between 9 a.m. and 4 p.m. and will be escorted by pilot cars and flaggers.

Please call us 24 hours a day at (866) 973-1476 with any concerns about the construction!


Foundation and wall of new Treated Water Reservoir, Harry Tracy Water Treatment Plant.