Join us for a Community Coffee at Starbucks on May 20th
Please join us for coffee and casual discussion on Thursday, May 20th from 9:30am to 11am at Starbucks Coffee in Crystal Springs Village, located at 100 De Anza Blvd, #111, San Mateo.
Chat with the project team, ask questions and learn more about this project. Free coffee! Yippee!
Wednesday, May 19, 2010
Friday, April 30, 2010
Stormwater pollution prevention and erosion control on the New Crystal Springs Bypass Tunnel Project


photos of top layer, showing erosion control blanket
Last Saturday and early this week the contractor installed some very visible Best Management Practices (BMPs) for stormwater pollution prevention and erosion control in the muck disposal area on the upper terrace of the South Shaft Site. This erosion control blanket helps prevent stormwater pollution and will also help with dust control as summer approaches. Eventually the blankets will be replaced by topsoil and revegetation.
Friday, April 9, 2010
New Crystal Springs Bypass Tunnel - What to Expect the Next 6 Months
What Neighbors Can Expect the Next Six Months at the New Crystal Springs Bypass Tunnel site:
Removal of TBM components from the South Shaft site.
Installation and welding of steel pipe in the tunnel and South Shaft.
Construction of near-surface vaults, pipelines and miscellaneous equipment at South Shaft site and off of Polhemus Road.
Final grading of muck disposal area at the South Shaft site.
Re-vegetation of muck disposal area with native plant seed mixes prior to the Fall rainy season. Temporary dust control measures will be implemented.
If you ever have questions, you can call our toll-free, 24 hour phone at 866-973-1476.
Removal of TBM components from the South Shaft site.
Installation and welding of steel pipe in the tunnel and South Shaft.
Construction of near-surface vaults, pipelines and miscellaneous equipment at South Shaft site and off of Polhemus Road.
Final grading of muck disposal area at the South Shaft site.
Re-vegetation of muck disposal area with native plant seed mixes prior to the Fall rainy season. Temporary dust control measures will be implemented.
If you ever have questions, you can call our toll-free, 24 hour phone at 866-973-1476.
Thursday, March 25, 2010
Tunnel Excavation is Complete!!
A new steel pipe will soon be installed inside the 4,200 foot long tunnel to provide a critical link in the Hetch Hetchy water system.
The new pipeline will also help to ensure water delivery after a major earthquake.
Tuesday, March 23, 2010
TBM Expected to Reach North Shaft Within Hours!
The Tunnel Boring Machine (TBM) excavating the New Crystal Springs Bypass Tunnel is expected to reach the North Shaft site in a matter of hours!
The project team expects the TBM could finish as early as tomorrow, March 24th.
Watch this blog for updates!
The project team expects the TBM could finish as early as tomorrow, March 24th.
Watch this blog for updates!
Wednesday, March 17, 2010
Tunnel Boring Machine to Reach North Shaft Very Soon!
The Tunnel Boring Machine (TBM) boring the New Crystal Springs Bypass Tunnel is expected to reach the North Shaft site very soon!
The project team expects the TBM to finish boring next week - most likely on or around the 25th of March.
The TBM is boring a 4,200 foot long tunnel for a critical water pipeline that will help ensure water delivery after a major earthquake.
We will keep you updated on the tunnel completion and next steps in this important project.
Tuesday, March 2, 2010
SFPUC Labor Relations Efforts Paying Off During Economic Downturn
New Crystal Springs Bypass Tunnel contractor Shank/Balfour Beatty has 27% of its workforce hours in apprenticeship, exceeding the California Division of Apprenticeship Standards requirement of 20%, according to the WSIP Labor Relations Office. The contractor is also providing tunneling equipment on loan to the Northern California Laborers Apprenticeship Program for use in training programs, reports Ardis Graham, Project Labor Agreement Administrator.
For crane and equipment apprentice Simon Streeter and welding apprentice Justin Stephens, the PLA’s initiatives have resulted in opportunities to learn new, transferable skills through the Tunnel project. “We’re learning from guys with many years of experience. They look out for us. It is great to be employed in a good paying job where I learn something new each day,” said Streeter. Both men are residents in the WSIP service area.
Photos: Simon Streeter (top) and Justin Stephens (bottom).