Regional Groundwater Project Celebrates One Year in Construction

In April 2015, the Regional Groundwater Storage and Recovery project kicked off construction at the Linear Park site in South San Francisco. Only one year later, the project is more than 32 percent complete and overcoming construction challenges to reach the finish line.


Workers install steel rebar to prepare for the wall pours at the Linear Park well station in July 2015. On the right is the completed exterior of the Linear Park well station in March 2016.


In November 2015, the project started well drilling activities at the Treasure Island site in South San Francisco. The project completed drilling all wells apart of this contract in early 2016.


Construction crews finished installing new pipeline on South Spruce Avenue in South San Francisco in March 2016.

With these milestones successfully complete, the project team knows there is still a lot of work to be done before completion in October 2017.