Thursday, March 20, 2014

Harry Tracy Work Schedule Update

The Harry Tracy Water Treatment Plant is scheduled to resume full operations by April 1st. Since late February, water treatment has been “shut down” to allow for specific construction activities.

The weekend of March 22 and 23, the project team will work both Saturday and Sunday from 7 a.m. to 5 p.m. We expect indoor activities only before 9 a.m. and on Sunday.

The plant is typically online during construction, drawing and treating water from the Crystal Springs Reservoir System for delivery to wholesale customers. To accommodate project construction and connections to the system, it is taken off-line for limited periods.

If you have any questions or concerns about the project, please call us 24-hours a day at (866) 973-1476.

No comments:

Post a Comment