Thursday, March 20, 2014

Harry Tracy Work Schedule Update

The Harry Tracy Water Treatment Plant is scheduled to resume full operations by April 1st. Since late February, water treatment has been “shut down” to allow for specific construction activities.

The weekend of March 22 and 23, the project team will work both Saturday and Sunday from 7 a.m. to 5 p.m. We expect indoor activities only before 9 a.m. and on Sunday.

The plant is typically online during construction, drawing and treating water from the Crystal Springs Reservoir System for delivery to wholesale customers. To accommodate project construction and connections to the system, it is taken off-line for limited periods.

If you have any questions or concerns about the project, please call us 24-hours a day at (866) 973-1476.

Sunday, March 9, 2014

Truck Hauling on Helen Drive, March 10 to 14

Crews from the nearby Crystal Springs/San Andreas Transmission System Upgrade project are seismically reinforcing a tunnel at San Andreas Lake.

From March 10th through 14th , trucks will be using the Helen Gate entrance of the Harry Tracy Water Treatment Plant to deliver a lightweight type of concrete called “cell-crete.”

We expect approximately 10 round trips a day along Helen Drive in Millbrae during the project work hours, 7 a.m. to 6 p.m. Flaggers will be present for safety and trucks will be scheduled to avoid the Meadows Elemetary School drop-off and pick-up times.

A wheel washing station is set up at the plant’s exit to clean truck tires before they return to Millbrae streets.

Please call us 24-hours a day with any questions or concerns about this work at (866) 973-1476.

Sunday, March 2, 2014

San Bruno Traffic Advisory for March 3rd and 4th

On Monday morning, March 3rd, a large crane will be delivered to the Harry Tracy Water Treatment Plant in San Bruno before 7 a.m. in order to avoid the morning rush hour. The crane will be escorted and piloted up Crystal Springs Road from Cunningham Drive.

On both Monday and Tuesday, March 3 and 4, large machinery will be delivered to the plant between 9:15 a.m. and noon. We expect traffic delays on Crystal Springs Road between Cunningham and Crestmoor Drive during these periods.

Traffic control specialists will direct traffic through one open lane on Crystal Springs Road for most of the morning. The entire road will close for approximately 10 minutes for the equipment to turn the corner into the plant entrance.

Please call us at (866) 973-1476, 24-hours a day, with any questions or concerns.