Thursday, February 7, 2013

CONSTRUCTION NOTICE: Upcoming Evening and Saturday Work

The contractor will be working extended hours inside the Harry Tracy Water Treatment Plant beginning this Friday, February 8th with work near the gate at Crystal Springs Road and Crestmoor Drive. Lights may be visible in the area during the evenings. No roads will be closed nor will traffic be impacted by this work.

The work includes backfill around a 96” pipe for the new treated water reservoir. Necessary backfill material will be brought in during the week between 9 am and 4 pm.

Dates:
Friday, Feb. 8, 7:00 am to 7:30 pm
Saturday, Feb. 9, 9:00 am to 6:30 pm
Monday, Feb. 11, 7:00 am to 7:30 pm
Tuesday, Feb. 12, 7:00 am to 7:30 pm
Wednesday, Feb. 13, 7:00 am to 7:30 pm
 

Morning at Harry Tracy
This work is necessary as the crews prepare to make critical connections at the plant during the next two months.

Questions?
Please call our 24-hour hotline at (866) 973-1476.
You may also SUBSCRIBE to this blog for email updates: see box to the right.