Pile Driving 90% Complete

As of October 5th, 90% of the piles have been driven for the new Treated Water Reservoir. We expect approximately 7 additional days of pile driving, weekdays only.

Pile driving is currently scheduled to finish on October 16th. Any delay past this date would involve a short break in pile driving for the delivery of materials. Please subscribe to this blog to track our progress. (Enter your email into the box on the right-hand side of this page. You will receive a confirmation link via email. Click on the confirmation link to finalize your subscription. You can easily unsubscribe at any time).

This site will also have weekly updates about night work and other work activities during the plant operations shutdown from October 15th to December 10th. Water service to your home will not be impacted.

Please call us at (866) 973-1476 with any questions or concerns about the Harry Tracy project.

Pile driving nears completion for the Harry Tracy project.  