Harry Tracy Pile Driving – Almost There!

We are certain you would like us to report that the pile driving for the new Treated Water Reservoir foundation is complete.   However, approximately 50 piles remain out of more than 800 driven since early August.

The crews have encountered a soft section of earth that requires long piles. These piles are driven in easily and are subsequently “split.”   The splitting is a quieter activity that uses the same machinery.   This intermittent pile driving may continue through the middle of next week as we wrap up the final pile driving for the project.

Please subscribe (see right) to track our progress and receive automatic email updates. We will update this site every few days until the pile driving is 100% complete.

Pile driving hours are 7 a.m. to 6 p.m., weekdays only. No outdoor night work is currently scheduled.   

Please call us at (866) 973-1476 with any questions or concerns.