Harry Tracy Water Treatment Plant Update – Week of October 1st

October 1 - 12, the contractor will be working on an electrical vault near Crystal Springs Road from approximately 7 a.m. to 7 p.m. (weekdays only) and 9 a.m. to 5 p.m. on Saturdays. If you live on Crystal Springs Road, you may be able to hear this work. Please call us at (866) 973-1476 or email peninsula@sfwater.org if you have any questions or problems.

Pile driving is now more than 80% complete and is now expected to be complete by October 16. Please subscribe to this blog (by entering your email on the right-hand side of this page) to receive automatic email updates about the progress. The piles are to anchor the foundation of the new 11 million gallon Treated Water Reservoir. This is the final phase of pile driving for the Harry Tracy project.







All trucks use the wheel washer before exiting the plant to minimize dirt tracked onto Crystal Springs Road.