Harry Tracy Construction Update

Night work at the Harry Tracy Water Treatment Plant will take place next Monday, May 14th through Friday, May 18th.

Work hours for the temporary night shift are 5 p.m. to 1 a.m.  Crews will be excavating a pipe in the main road within the plant as part of the seismic upgrade of the water system. The work on the plant’s main road must be done at night so that daily Operations and regular construction activities may continue during the day.

Our contractor will monitor noise each night to ensure levels comply with local ordinances. All work will take place within the plant and no haul trucks will be on the public roadways during the night shift. Night lighting will be confined to the specific work area. 

We apologize in advance for any disturbance and invite you to call our 24-hour phone line at (866) 973-1476.