Harry Tracy Water Treatment Plant: Construction Update

Work to excavate the site of our new 11 million gallon Treated Water Reservoir continues at our Harry Tracy Water Treatment Plant in Millbrae.  This reservoir, which holds drinking water before it enters the distribution system, is being relocated within the plant to a more seismically stable area.

Additional truck traffic along Crystal Springs Road will continue, as materials are delivered and the excavated soil is removed.

The plant must maintain water treatment operations 24 hours a day, 7 days a week throughout the 4 years of construction. Coordinating the continued operation of the plant while reconfiguring and relocating systems is a complicated challenge for our contractors and operations staff!

We are making every effort to minimize construction impacts to your neighborhood. Please let us know your concerns and comments by contacting us at (866) 973-1476…or by attending our Open House on November 14th.

Informational Open House on construction at our Harry Tracy Water Treatment Plant
Date: Monday, November 14th
Time: 7:00 p.m. to 8:30 p.m.
Location: San Bruno Recreation Center
Community Room, 251 City Park Way
Directions: The San Bruno Recreation Center is located inside San Bruno City Park near the intersection of Crystal Springs Rd. and Oak Ave.

Our project team will be on-hand to answer any questions you have about the Hetch Hetchy Regional Water System, current system-wide upgrades, as well as construction project updates. This is an informal drop-in event – stop by any time! 