Friday, May 6, 2011

Demobilization Continues near Polhemus Rd & Crystal Springs Rd in San Mateo

Crews continue to remove equipment and materials from both the north and south shaft construction sites of the New Crystal Springs Bypass Tunnel & Pipeline project in San Mateo.


Early next week, crews will remove the k-rail along Crystal Springs Road near the former north shaft construction area (the 10 mph zone near Polhemus Road). Metal guard rail will be installed and crews will be working on the shoulder area. Please watch for crews in the area and use caution during this work next week.

Top soil deliveries will continue to the south shaft site along Polhemus Road. Please watch for trucks in the area during the day. Dust mitigation measures will be in effect to minimize dust.


Construction trailers will be removed from the site soon.

No comments:

Post a Comment