SFPUC to begin Prepping for Installation of San Andreas Pipeline No. 3

The San Andreas Pipeline No. 3 Installation will be replacing an aging pipeline, with a newly constructed 4 miles extension from Daly City to San Francisco.

Work will commence near the County line and proceed north. Construction south of John Daly Boulevard will begin after January 2010.

In early September, SFPUC will begin preliminary stages of the construction project by potholing, or verifying the existing placement of pipelines and other utilities. Potholing is expected to be completed by the end of October 2009.


What to expect?
Contractor will need to restrict parking around locations where potholing will take place. Advance notice will be given 72-hours in advance.

If work is not commenced prior to noon, parking is available to the public.


Workdays and Hours
Monday-Friday 7:00 am - 5:00 pm

No construction will occur outside of these posted hours without advanced written notice.


Traffic
Minimal traffic impact, possible detours.


Noise
Noise levels will be in compliance with San Francisco Noise Ordinance and the noise will be limited to the immediate work areas.

Complete construction duration for San Andreas Pipeline No. 3 will be from:
September 2009 - January 2012

For more information on San Andreas Pipeline No. 3, please visit sfwater.org/wsip