Tuesday, August 18, 2009

Blast Schedule for Remainder of Week

Controlled blasts are scheduled for Wednesday at 11:00 am, Thursday at 9:00 am, and Friday at 10:00 am. We will provide you with updates if conditions in the field dictate any changes to the schedule.

The anticipated finish time for the controlled blasts is about one month or less with 4-5 shots per week. The starter tunnel is now 80 feet long. Final length will be approximately 100 feet.

The contractor continues to perform within the thresholds for noise, vibration and air quality standards. Measurements are conducted daily.

Dust Mitigation
The project contractor has implemented additional mitigation measures in response to dust complaints from neighbors.